To install an arbor:

1.UNPLUG THE MILL/DRILL!

2.Slide the arbor into the spindle, ensuring that the arbor keyway aligns with the pin inside the spindle.

3.While holding the arbor in place, turn the drawbar clockwise until the drawbar engages with the arbor.

4.Continue turning the drawbar until the arbor is firmly secured in place.

To remove an arbor:

1.UNPLUG THE MILL/DRILL!

2.Using a 17mm wrench, turn the drawbar hex nut counterclockwise two turns, as shown in

Figure 10.

Figure 10. Turning the drawbar nut.

3.Strike the end of the drawbar with a dead blow mallet to unseat the arbor from the spindle.

4.While holding the arbor, unscrew the drawbar until the arbor comes free.

G1005Z Mill/Drill

To install end mill tooling:

1.UNPLUG THE MILL/DRILL!

2.Insert the appropriate-sized R8 collet into the spindle, ensuring that the collet keyway aligns with the pin inside the spindle.

3.Using a heavy rag or gloves to protect your hands, insert the end mill tooling into the collet.

4.While holding the collet in place, turn the drawbar hex nut clockwise until the drawbar engages with the collet.

5.Turn the drawbar nut clockwise until the tool- ing is completely secured in the collet.

To install the drill chuck:

1.UNPLUG THE MILL/DRILL!

2.Ensure that both the arbor and chuck are clean, dry and free of dirt, debris or grit.

3.Slide the chuck onto the arbor.

4.Securely seat the chuck in place by giving it a single hard tap with a rubber mallet, as shown in Figure 11.

Note: Once the chuck is seated on the arbor, it is

asemi-permanent connection. If you wish to use

adifferent chuck, we recommend obtaining a new arbor for that chuck.

Figure 11. Seating the JT6 drill chuck.

-17-

Image 19
Contents Model G1005Z MILL/DRILL Page Table of Contents Foreword IntroductionContact Info Machine Data Sheet Lead Screw Info Identification Safety G1005Z Mill/Drill Additional Safety for Mill/Drills Circuit Requirements Circuit Requirements110/220V Operation Amperage Draw220V Operation GroundingExtension Cords 110V OperationUnpacking SET UPSet Up Safety Items Needed for SetMain Components Figure Qty InventoryOther Components and Hardware Operational Clearances Clean UpSite Considerations Workbench LoadTo assemble the Model G1005Z MountingAssemblyTo test run the machine Test RunTo install tooling on included mill arbor Operation SafetyInstalling/Removing Tooling Using Clean TapersTo remove an arbor To install an arborTo install end mill tooling To install the drill chuckCross Feed To install a drill bitTo remove a drill bit Longitudinal FeedTo correct for backlash Graduated DialsMicro-Downfeed Handwheel BacklashDepth Stop Quill LockLubrication Suggestions Using the Drill Bit Speed ChartChoosing Milling Speeds Choosing Drilling SpeedsDrill bit speed chart To change speeds Changing SpeedsDrilling Guidelines H2689-R8 Quick Change Collet Set AccessoriesH1300 H1298 G7984 H2347 H0736 Unpainted Cast Iron MaintenanceCleaning ScheduleTroubleshooting ServiceMotor & Electrical Operation Symptom Possible Cause Possible SolutionSymptom Possible Cause Possible Solution To calibrate the depth stop Depth Stop Feed Shaft Spring CalibrationPage G1005Z Junction Box G1005Z Mill/Drill Electrical ComponentsWiring Diagram G1005Z Description G1005Z Main Assembly Parts ListG1005Z Table Breakdown G1005Z Table and Labels Parts List Warranty and Returns Page Page