SECTION 14: GENERAL SPECIFICATIONS

SECTION 14: GENERAL SPECIFICATIONS

 

14.1 Material Specifications

14.3 Suspension Specifications

14.1.1 Reflectors

Hang heater with materials with a minimum working

.024 Aluminum

load of 75 lbs (33 kg). See Page 15, Figure 14.

(Optional .024 Stainless Steel Type 304)

14.4 Controls Specifications

14.2 Heater Specifications

Time switches, thermostats, etc. can be wired into

14.2.1 Ignition

the electrical supply. External controls supplied as an

Fully automatic, three-try, direct spark, electronic

optional extra.

 

ignition control, 100% safety shut-off.

General Specifications for BH-Series heaters are as follows:

End View

Side View

 

Reflector

 

 

 

 

 

 

 

 

 

12.5"

 

 

 

 

Turbulator (select models)

(32 cm)

 

 

 

 

 

 

 

 

 

 

12.5"

 

 

Burner Tube

Minimum Length A

 

 

11"

 

 

 

 

(32 cm)

 

 

 

 

 

(28 cm)

 

 

 

 

 

 

 

 

 

 

 

 

Heat Input Rate

Length “A”

Recommended

 

 

Minimum Mounting Height*

 

 

 

 

Model

(Btu/h) x (1000)

Minimum

Space

Spot

BH-40

40

10' (3 m)

8-10' (2.4 - 3 m)

8'(2.4 m)

BH-60

60

20' (6 m)

10-12' (3 - 3.6 m)

9' (2.7 m)

BH-80

80

20' (6 m)

12-15' (3.6 - 4.5 m)

11'

(3.3 m)

BH-100

100

30' (9 m)

12-15' (3.6 - 4.5 m)

12'

(3.7 m)

BH-115

115

30' (9 m)

15-20' (4.5 - 6 m)

15'

(4.6 m)

BH-125

125

40'

(12 m)

15-20' (4.5 - 6 m)

15'

(4.6 m)

BH-140

140

40'

(12 m)

20-25' (6 - 7.6 m)

20'

(6.1 m)

BH-150

150

50'

(15 m)

20-25' (6 - 7.6 m)

20'

(6.1 m)

BH-175

175

50'

(15 m)

25' (7.6 m)

23' (7 m)

BH-200

200

60'

(18 m)

25' (7.6 m)

25'

(7.6 m)

*See Page 5, Section 3 for clearances to combustibles.

GAS PRESSURE AT MANIFOLD:

Natural Gas:

3.5" wc

LP Gas:

10.5" wc

PIPE CONNECTION:

1/2" NPT (for BH-40, 60, 80, 100, 115 & 125) 3/4" NPT (for BH- 140, 150,175 & 200)

DIMENSIONS:

Vent Connection Size: 4" (10 cm)

Outside Air Connection Size: 4" (10 cm)

Refer to figure above for dimensional information.

GAS INLET PRESSURE:

 

 

Natural Gas:

 

 

for BH-40, 60, 80, 100,

 

 

115, 125, 140, 150

4.6" wc Minimum

for BH-175, 200

5.0" wc

Minimum

 

14.0" wc

Maximum

LP Gas:

11.0" wc

Minimum

 

14.0" wc Maximum

ELECTRICAL RATING (ALL MODELS):

120 V - 60 Hz, 1 A

57 of 59

Image 63
Contents Installation must be done by a contractor qualified Improper installation, adjustment, alteration, serviceOr maintenance can result in death, injury or Property damage. Read the Installation, OperationPage Roberts-Gordon LLC Page Table of Figures Page California Proposition Heater SafetyManpower Requirements Safety Labels and Their PlacementTop and Bottom Panel Label Placement Side and Back Panel Label Placement Installer Responsibility Wall TagNational Standards and Applicable Codes Clearances are the required distances that Maintain clearances to combustibles at all times for safetyModel InchesC D CentimetersTube, Standard Reflector Model 45 Tilt Reflector ModelInches Centimeters Tube, Opposite 45 Reflector ModelCentimeters Model Venting InchesNational Standards and Applicable Codes Reflector End Cap Major ComponentsStainless Steel Burner TubeStandard Parts List Contents of BH-Series Burner CartonContents of Core and Extension Packages BH-Series Component Package Guide Model Tubing Length Core Packages Minimum Standard AluminizedHeater Installation Typical Suspension Details Linear Heater Assembly Overview Linear Heater Layout Overview Linear Heater Layout Overview Burner Tube InstallationClosed Tube Clamp Package InstallationCoupling and Tube Assembly Open2 Coupling and Tube Assembly 1 Coupling and Tube AssemblyNot required on the BH-125/150/175/200 Turbulator InstallationHanger Burner Tube Reflector Description Part Number Reflector Support Package 1 Reflector, U-Clip and Reflector Support InstallationBurner Installation Optional Heater Accessories Tube, Standard TubeTube, Opposite Tube Heater Layout Overview Tube Layout Overview Elbow Package Configuration .2.1 Elbow Installation2 Elbow Installation Reflector Joint Detail 5 Reflector Joint Detail2 Side Reflector Installation Reflector Side Extension 1 Bracket InstallationDescription Part Number Lower Clearance Shield Package Distance a Extension 2 Frame Shield Installation3 Grille Installation 2 Grille End Cap InstallationVenting United States RequirementsCanadian Requirements Unvented Operation Tube Termination Unvented OperationHorizontal Venting Vertical VentingVertical Ventilation 4 10 cm Pipe Common Side Wall VentingOutside Wall Common Vertical Venting Outside Combustion Air Supply Vertical Outside Air Supply for Single Heater InstallationHorizontal Outside Air Supply for Double Heater Installation Vertical Outside Air Supply for Double Heater InstallationGAS Piping Failure to follow these instructions can result When attaching gas hoseCorrect Positions Hold gas nipple securely with pipe wrenchLine Voltage Thermostat Wiring WiringFront View Low Voltage Thermostat WiringInternal Wiring Ladder Diagram Electrical Connection to the Burner To Shut Off Heater Operation and MaintenancePre-Season Maintenance and Annual Inspection Sequence of OperationReflector Vicinity of the HeaterVehicles and Other ObjectsElectrode Safety LabelsBlower Scroll, Wheel Motor Burner Cup and OrificeTroubleshooting YES Troubleshooting Flow ChartPage Manifold Gas Pressure Setting Replacement Parts Replacement Parts Description Part Number Pipe Connection General SpecificationsDimensions GAS Pressure AT ManifoldPage Limitations on Authority Representatives Warranty is Void ifROBERTS-GORDON LLC will PAY for ROBERTS-GORDON LLC will not PAY forPage Page Page