Weil-McLain 230, 310, 105, 155 manual Connect condensate drain, Condensate drain Ultra-80

Page 20

4 GAS-FIRED WATER BOILER — Boiler Manual

Venting, combustion air & condensate line (continued)

Connect condensate drain

Figure 12 Condensate drain — Ultra-80 & -105

1.Remove condensate trap line from bag. Prepare and install per page 19. Secure to jacket by attaching PVC tee as shown in Figure 13.

2.Slide trap line onto flue outlet condensate connection and PVC reducing elbow as shown in Figure 12, 13 or 14. Secure with hose clamps.

3.Connect condensate drain tubing to the ½" PVC tee and run to floor drain or condensate pump. Use ½" PVC or CPVC pipe; or 5/8" I.D. tubing.

Use materials approved by the authority having jurisdiction. In the absence of other authority, PVC and CPVC pipe must comply with ASTM D1785, F441 or D2665. Cement and primer must comply with ASTM D2564 or F493. For Canada, use CSA or ULC certified PVC or CPVC pipe, fittings and cement.

4. Leave the top of the ½" tee OPEN. This is needed as a vacuum break.

Figure 13 Condensate drain — Ultra-155 & -230 (PVC tee installation shown applies to all models))

5.When installing a condensate pump, select one approved for use with condensing boilers and furnaces. The pump should have an overflow switch to prevent property damage from condensate spillage.

6.Condensate from the Ultra boiler will be slightly acidic (typically with a pH from 3.2 to 4.5). Install a neutralizing filter if required by local codes.

The condensate line must remain unobstructed, allowing free flow of condensate. If condensate is allowed to freeze in the line or if the line is obstructed in any other manor, condensate can exit from the boiler tee, resulting in potential water damage to property.

Figure 14 Condensate drain — Ultra-310

20

Part number 550-101-233/0903

Image 20
Contents Gas-fired water boiler HOW IT Works GAS-FIRED Water BOILER, with PhD Technology Contents Hazard definitionsWhen servicing boiler Please read before proceedingBoiler operation Boiler waterInstallations must comply with Prepare boiler locationBefore locating the boiler, check Provide clearancesResidential garage installation Flooring and foundationProvide air openings to room Vent and air pipingSeal any unused openings in the common venting system When removing a boiler from existing common vent systemPrevent combustion air contamination Prepare for propane if operating on propane Ultra-80 Prepare boilerRemove boiler from crate Prepare for propane if operating on propane Ultra-155 to Placing floor-mounted boilersPlacing wall-mounted boilers Set boiler in place and check levelPerform hydrostatic pressure test Prepare boiler for testFill and pressure test Drain and remove fittingsInstall water piping Install relief valveAdditional controls, when required General piping informationSizing space heat system piping System water piping methodsCirculators Sizing DHW system piping Required boiler water flow rate, GPM, at 180FControlling the system circulator Zoning with zone valvesConnect boiler to system as shown in when Zoning with circulators Setting boiler outlet water target temperature Radiant heating applicationsChilled water systems Chilled water system plus optionalPrepare condensate fittings Install vent and combustion air pipingVenting, combustion air & condensate line Connect condensate drain Condensate drain Ultra-80Wall-mounted boilers Connecting gas supply pipingGas piping Natural Gas Propane GasPipe sizing for natural gas Natural gas supply pressure requirementsFreeze protection when used StartupCheck/control water chemistry Fill and test water systemCheck for gas leaks Final checks before starting boiler Check thermostat circuitsInspect/fill condensate system To start the boilerCheck flame & combustion Adjust and test boiler controlsCheck system and boiler Check-out/startup verification Check-out/startup verification Installation certificate Annual startup and general maintenance Service and maintenance schedulesAnnual startup Handling ceramic fiber materialsClean condensate trap Check water systemCheck all piping for leaks Check expansion tank Check air openingsCheck ignition ground wiring Check all boiler wiringCheck control settings Check boiler relief valveCheck flame signal Check flue gas temperaturePerform startup and checks Check burner flameMaintenance general General maintenanceCleaning boiler heat exchanger Replace boiler jacket front door after startup or servicingExchanger cleaning ALL models Maintenance and annual startupAccess exchanger Ultra-155, -230, -310 Only Replacement parts Jacket parts Replacement parts Heat exchanger and piping Ultra-80 Replacement parts Heat exchanger and piping Ultra-155 to Replacement parts Controls Dimensions Ratings DOE