7
Check-out/startup verification
❏Boiler and heat distribution units filled with water?
❏Water chemistry verified per page 23?
❏Automatic air vents, if used, open one full turn?
❏Air purged from system?
❏Air purged from gas piping? Piping checked for leaks?
❏Propane orifice installed for propane firing and propane conversion label affixed to jacket?
Ultra boilers are shipped ready to fire natural gas ONLY. Exception: The Ultra- 80LP is
❏Thermostat circuit wiring checked to ensure there are no stray voltages per page 24, “Check Thermostat Wires?”
❏Followed Operating Instructions in Ultra Control Supplement?
❏Burner flame and combustion verified per page 25?
❏Verified control operation for space heating and DHW (if used) per Ultra Control Supplement?
❏Tested additional
❏Set additional
❏For multiple zones, adjusted for correct flow in each zone?
❏Verified thermostat heat anticipator (if available) set properly? Refer to Ultra Control Supplement.
❏Cycled boiler with thermostat (and with DHW aquastat, if installed) — Raised to highest setting and verified boiler goes through normal startup cycle? Lowered to lowest setting and verified boiler goes off?
❏Measured natural gas input? (per page 25)
❏Checked incoming gas pressure by connecting manometer to gas valve ahead of boiler? (Gas pressure must be at least 5 inches w.c. for natural gas, and 4 inches w.c. for propane, with boiler operating at high fire, and no more than 13 inches w.c. with boiler operating or boiler off.)
❏Observed several operating cycles for proper operation.
❏Set room thermostat to desired room temperature (and DHW aquastat, if installed, to desired DHW storage temperature)?
❏Reviewed all instructions shipped with this boiler with owner or maintenance person?
❏Fill in Installation certificate on page 27.
❏Return instructions to envelope and give to owner or place inside boiler housing.
26 | Part number |