Desa CDVBPC, CDVBNC Installation for Vertical Termination, Flat Ceiling Installation

Page 15

VENTING INSTALLATION

Installation For Vertical Termination

15

VENTING INSTALLATION

Continued

INSTALLATION FOR VERTICAL

TERMINATION

NOTICE: Use rigid pipe only. Flex venting is not to be used with a vertical termination.

1.Determine the route your vertical venting will take. If ceiling joists, roof rafters, or other framing will obstruct the venting system, consider an offset (see Figure 30) to avoid cutting loadbearing members. Note: Pay special attention to these in- stallation instructions for required clearances (air space) to com- bustibles when passing through ceilings, walls, roofs, enclo- sures, attic rafters, etc. Do not pack air spaces with insulation. Also note maximum vertical rise of the venting system and any maximum horizontal offset limitations. Offsets must fall within the parameters shown in Figure 18 on page 10.

2.Set the stove in desired location. Drop a plumb line down from the ceiling to the position of the burner system exit flue. Mark the center point where the vent will penetrate the ceiling. Drill a small locating hole at this point.

Drop a plumb line from the inside of the roof to the locating hole in the ceiling. Mark the center point where the vent will penetrate the roof. Drill a small locating hole at this point.

Roof

Flashing

Wall Strap

45° Elbow

Ceiling Firestop

Figure 30 - Offset with Wall Strap and 45° Elbows

Flat Ceiling Installation

1.Cut a 10" square hole in the ceiling using the locating hole as a center point. The opening should be framed to 10"x10" (254mm x 254mm) inside dimensions, as shown in Figure 22 on page 13 using framing lumber the same size as the ceiling joists. If the area above the ceiling is an insulated ceiling or a room, nail firestop from the top side. This prevents loose insulation from falling into the required clearance space. Otherwise, install firestop below the framed hole. The firestop should be installed with no less than three nails per side (see Figure 31).

2.Assemble the desired lengths of pipe and elbows necessary to reach from the burner system flue up through the firestop. All connections must be sealed with high temperature silicone seal- ant as specified in the second warning statement on page 11. Be sure all pipe and elbow connections are fully twist-locked (see Figure 21, page 13).

3.Cut a hole in the roof using the locating hole as a center point. (Cover any exposed open vent pipes before cutting hole in roof.) The 10"x10" hole must be measured on the horizontal; actual length may be larger depending on the pitch of the roof. There must be a 1" clearance from the vent pipe to combustible mate- rials. Frame the opening as shown in Figure 22 on page 13.

4.Connect a section of pipe and extend up through the hole.

Note: If an offset is needed to avoid obstructions, you must support the vent pipe every 3 feet. Use wall straps for this purpose (see Figure 30). Whenever possible, use 45° elbows instead of 90° elbows. The 45° elbow offers less restriction to the flow of the flue gases and intake air.

5.Place the flashing over the pipe section(s) extending through the roof. Secure the base of the flashing to the roof and fram- ing with roofing nails. Be sure roofing material overlaps the top edge of the flashing as shown in Figure 30. There must be a 1" clearance from the vent pipe to combustible materials.

6.Continue to add pipe sections until the height of the vent cap meets the minimum building code requirements described in Figure 18 on page 10. Note: You must increase vent height for steep roof pitches. Nearby trees, adjoining rooflines, steep pitched roofs, and other similar factors may cause poor draft or down-drafting in high winds. Increasing the vent height may solve this problem.

7.Twist-lock the vent cap onto the last section of vent pipe and seal outer pipe connection with high temperature silicone seal- ant as specified in the second warning statement on page 11.

Note: If the vent pipe passes through any occupied areas above the first floor, including storage spaces and closets, you must enclose pipe. You may frame and sheetrock the enclosure with standard construction material. Make sure and meet the minimum allowable clearances to combustibles. Do not fill any of the required air spaces with insulation.

If area above is a room, install

If area above is not a room, install

firestop above framed hole.

firestop below framed hole.

Figure 31 - Installing Firestop

For morevisit www..com

105501-01F

Image 15
Contents OWNER’S Operation and Installation Manual For Your SafetyFor Your Safety What to do if YOU Smell GAS Safety Information Table of ContentsCleaning stove or burner system Safety Information Product IdentificationGlossary of Terms Product FeaturesPRE-INSTALLATION Preparation Local CodesClearance for Corner Installation Stove Body Assembly Cast Iron Stove and DIRECT-VENT Burner System AssemblyCatch Bolt and Door Claw Orientation Installing DIRECT-VENT Burner System Into Stove BodyInstalling GA3750/CDA3620T Blowers Installing Optional Blower AccessoryInstalling Rear Cover General VentingLocation of Vent Termination General Venting Venting Installation Installation PrecautionsInstallation Planning Installing Vent System in a Chase Installation for Horizontal TerminationInstalling Horizontal Vent Cap Noncombustible Exterior Horizontal Termination Configuration for Rigid Venting Horizontal Termination ConfigurationsFlat Ceiling Installation Installation for Vertical TerminationVertical Termination Configurations Cathedral Ceiling InstallationParts Lists for Venting Kits and Components High Altitude InstallationCheck GAS Type Stove and DIRECT-VENT Burner System InstallationInstalling GAS Piping to STOVE/ Burner System Location Installation Items NeededConnecting STOVE/BURNER System to GAS Supply Pressure Testing Gas Supply Piping SystemChecking GAS Connections Turn off burner system see To Turn Off Gas to Appliance, Pressure Testing Burner System Gas ConnectionsInstalling Remote Receiver Installing 9-Volt Battery in Hand-Held Remote Control UnitREMOVING/REPLACING Glass Door Removing Front Panel from Stove Installing LOGS, Lava Rock and Glowing EmbersFor Your Safety Read Before Lighting Operating Stove with Burner SystemLighting Instructions Shutting Off Burners Only pilot stays lit Manual Lighting ProcedureTo Turn OFF GAS To Appliance Optional Remote OperationOperating Optional Blower Accessory Cghrc Series OperationCghrcta Series Operation Burner Flame Pattern Pilot AssemblyInspecting Burners Operating Optional GWMT1 Wall Mounted ThermostatLogs Cleaning MaintenanceGlass Door Pilot and BurnersObserved Problem Possible Cause TroubleshootingObserved Problem Possible Cause Remedy Gas leak. See Warning statement Parts Under Warranty Wiring DiagramReplacement Parts SpecificationsCdvbnc Cdvbpc Illustrated Parts BreakdownParts List Parts ListStove Chassis Cisc Cisg KEY Part Description QTY Cisc CisgTechnical Service Service HintsAccessories Owners Registration Form Postage Required 105501-01F Warranty Information