12
INSTALLING
Continued
BUILT-IN FIREPLACE INSTALLATION
Height |
| Front Width | Depth | Bottom | ||||
|
|
|
|
|
|
|
| |
Actual | Framing | Actual | Framing | Actual | Framing | Actual | Framing | |
|
|
|
|
|
|
|
|
|
26" | 26 | 7/8" | 26 3/4" | 26 7/8" | 9 1/2" | 10 1/2" | 3/4" | 3/4" |
|
|
|
|
|
|
|
|
|
1.Frame in rough opening. Use dimensions shown in Figure 8 for the rough opening.
10 1/2"
26 7/8" |
| |
| 3/4" Off | |
26 7/8" | The Floor | |
Minimum | ||
|
Figure 8 - Rough Opening for Installing in Wall
If installing in a corner, use dimensions shown in Figure 9 for the rough opening. The height is 26 1/8" which is the same as the wall opening above.
36 5/8"
25 7/8"
26 7/8" 51 3/4"
Figure 9 - Rough Opening for Installing in Corner
2.An optional blower accessory is available (see Accessories, page 32). There are two options for connecting blower to electrical source.
Option one: Have a licensed electrician install a properly grounded, three- prong
Option two: Have a licensed electrician connect blower to electrical source at junction box inside fireplace.
If using option one, have electrical outlet installed at this time. If using option two, do not connect blower to electrical source at junction box until step 7.
3.Install gas piping to fireplace location. This installation includes an approved flexible gas line (if allowed by local codes) after the manual shutoff valve. The flexible gas line must be the last item installed on the gas piping.
4.If you have not assembled firebox, follow instructions on page 5.
5.Carefully set fireplace in front of rough opening with back of fireplace inside wall opening.