Williams 2903511, 2903512 installation instructions

Page 6

Figure 1

1 = Fixed/Closed

2 = Openable

V = Vent Terminal

A = Air Supply

A.Clearance above grade, veranda, porch, deck or balcony 12-inches (30 cm) minimum. (3)

B.Clearance to window or door that may be opened 12- inches (30 cm) minimum. (3)

C.Clearance to permanently closed window (minimum 12- inches (30 cm) recommended to prevent condensation on window.

K.Clearance to a mechanical air supply inlet 6-feet (1.8 m) minimum. (3)

L.Clearance (1) above paved sidewalk or a paved driveway located on public property 7-feet (2.1 m) minimum. (3)

M.Clearance under veranda, porch, deck or balcony 12- inches (30 cm) minimum. (2), (3)

D.Vertical clearance to ventilated soffit located above the terminal within a horizontal distance of 2-feet (60 cm) from the centerline of the terminal 18-inches (46 cm) minimum.

E.Clearance to unventilated soffit 12-inches (30 cm) minimum clearance to vinyl soffit 36-inches (90 cm) minimum.

F.Clearance to outside corner 12-inches (30 cm) minimum.

Notes:

(1)A vent must not terminate directly above a sidewalk or paved driveway which is located between two single family dwellings and serves both dwellings.

(2)Only permitted if veranda, porch, deck or balcony is fully open on a minimum of two sides beneath the floor.

(3)As specified in CGA B149 installation codes (1991).

G.Clearance to inside corner 18-inches (46 cm) minimum.

H.Not to be installed above a meter/regulator assembly within 3-feet (90 cm) horizontally from the centerline of the regulator. (3)

I.Clearance to service regulator vent outlet 6-feet (1.8 m) minimum. (3)

J.Clearance to nonmechanical air supply inlet to building or the combustion air inlet to any other furnace 12- inches (30 cm) minimum. (3)

Note: Local codes or regulations may require different clearances.

5

Image 6
Contents Direct-Vent Wall Furnace Table of Contents General Information and Technical DataSafety Rules and General Warnings Safety Information for Users of LP GasLP Gas Warning Odor Technical Data Some Points to RememberInstallation Wall InstallationPage Outside Location for Vent Terminal Ring Gasket Nozzle Diameter Gas ConversionsGas Type Nozzle Part Number Minimum Manifold Gas PressureGas Supply Installing a New Main Gas Shutoff ValvePressure Testing of the Gas Supply System High Altitudes U.S. OnlyFirst Firing of the Furnace Checking the Gas Inlet PressureChecking the Gas Manifold Pressure Electrical Wiring For Your Safety Read Before Operating Operating InstructionsWhat to do if the RED Lamp is LIT Lubrication of Moving Parts Checking and Adjusting the Gas Manifold PressureServicing Flame Visual CheckAnnual Maintenance Requirements Programmable Timer OverviewProgramming the Timer Setting and Adjustment Initial ConditionsDay and Time Setting Manual OperationUsing the Skip Function Cancelling a Single ProgramCancelling of all Preset Programs Skip Function Procedure During OperationTroubleshooting Starting Sequence ElectricalTroubleshooting Step Starting Sequence Gas Replacement Parts Gas AssemblyJMTR018