Troubleshooting

Starting Sequence (Electrical)

Step 1

1.Check L1 – L2 (Supply 120 V, 60 Hz)

2.Check M9 (Main fuse)

Troubleshooting Step 1

Point 1 (L1-L2)

No voltage (120 V).

Check the electrical supply line, wiring and connections.

Point 2 (M9) Fuse damaged.

Check the electrical supply line and replace the fuse.

Summer Mode

Step 2

3.Check Z1 (Reset summer/winter switch). The switch is closed if there is no ignition block.

4.Check Z2 (Hi-Lo flame and fan speed switch) Button down - Minimum velocity

Button up – Maximum velocity

Troubleshooting Step 2

Point 3 (Z1)

Z1 is open and no ignition.

Check wirings and connections. If everything is okay, replace the switch.

Point 4 (Z2)

Z2 is down but the fan motor runs at the maximum velocity (120 V).

Z2 is up but the fan motor runs at the minimum velocity (<120 V).

Check wiring and connections. If they are okay, replace the switch.

Winter Mode

Step 3

5.Check Z1 (Reset summer/winter switch).

Button up – winter mode.

6.Check Z3 (Manual-automatic switch). Button up – manual mode

Button down – automatic mode.

7.Check M2 (Fan thermostat).

The thermostat is closed only when its temperature is higher than 104 °F.

19

Image 20
Contents Direct-Vent Wall Furnace Table of Contents General Information and Technical DataLP Gas Warning Odor Safety Rules and General WarningsSafety Information for Users of LP Gas Technical Data Some Points to RememberInstallation Wall InstallationPage Outside Location for Vent Terminal Ring Gasket Gas Conversions Gas Type Nozzle Part NumberNozzle Diameter Minimum Manifold Gas PressureInstalling a New Main Gas Shutoff Valve Pressure Testing of the Gas Supply SystemGas Supply High Altitudes U.S. OnlyChecking the Gas Manifold Pressure First Firing of the FurnaceChecking the Gas Inlet Pressure Electrical Wiring For Your Safety Read Before Operating Operating InstructionsWhat to do if the RED Lamp is LIT Checking and Adjusting the Gas Manifold Pressure ServicingLubrication of Moving Parts Flame Visual CheckAnnual Maintenance Requirements Programmable Timer OverviewSetting and Adjustment Initial Conditions Day and Time SettingProgramming the Timer Manual OperationCancelling a Single Program Cancelling of all Preset ProgramsUsing the Skip Function Skip Function Procedure During OperationTroubleshooting Starting Sequence ElectricalTroubleshooting Step Starting Sequence Gas Replacement Parts Gas AssemblyJMTR018