Williams 1773511, 1773512 installation instructions Troubleshooting Step

Page 21
Manual background

Troubleshooting Step 3

Point 5 (Z1)

Z1 is open and no ignition.

Check wiring and connections. If everything is okay, replace the switch.

Point 7 (M2)

M2 is closed and fan thermostat temperature is lower than 104 °F.

Check wiring and connections. If they are okay, replace the thermostat.

Step 4

8.Check Z9 (Room thermostat). Close the thermostat with a clockwise rotation.

9.Check M1 (Overheat thermostat, automatic reset). The thermostat is closed at a temperature lower than 140 °F.

10.Check S (Combustion blower motor).

Troubleshooting Step 4

Point 8 (Z9)

After a clockwise rotation, the contact is still open. Check wiring and connections. If they are okay, and the room temperature is cold, replace the switch.

Point 9 (M1)

M1 is open and fan thermostat temperature is lower than 140 °F. Check wiring, connections, gas pressure and fan motor. Clean fan blades and air grids. If everything is okay, replace the thermostat.

Point 10 (S)

S motor does not run. Check voltage, wiring and connections.

If everything is OK, replace the motor.

Step 5

11.Check NP (Pressure switch).

12.Check electrical supply to flame control box (120 V).

13.Check TR (electrical transformer). (120V/24V)

14.Check EV1 (Min gas valve, 24V).

15.Check RP7 (ignitions electrode)

16.Check RP8 (flame sensor)

17.Check EV2 (Max gas valve, 24 V).

Troubleshooting Step 5

Point 11 (NP)

NP contact is open and air blower ON.

Check wiring and connections. Check and clean blower pipes.

Check and clean burner and flue gas pipe. Clean blower.

If everything is okay, replace the switch.

24 V

120 V

 

20

Image 21
Contents Direct-Vent Wall Furnace Williams Furnace Co., 250 West Laurel Street, Colton, CA 92324 U.S.AInstructions to Installer Table of Contents General Information and Technical DataSafety Information for Users of LP Gas Safety Rules and General WarningsLP Gas Warning Odor That’s your signal to go into immediate actionSome Points to Remember Technical DataWall Installation InstallationOutside Location for Vent Terminal Air inlet tube length = wall thickness + 3/32-inches 2.4 mmFlue outlet tube length = wall thickness + 1-5/16-inches 7.9 mm A + 33.3 mm 13. Relocate the vent cap and attach it with the screws. Figure Gas Type Gas ConversionsNozzle Part Number Nozzle DiameterInstalling a New Main Gas Shutoff Valve High Altitude AdjustmentPressure Testing of the Gas Supply System Gas SupplyChecking the Gas Inlet Pressure First Firing the FurnaceChecking the Gas Manifold Pressure A B CElectrical Wiring Diagram Key Operating Instructions FOR YOUR SAFETY READ BEFORE OPERATINGOPERATING INSTRUCTIONS TO TURN OFF GAS TO APPLIANCEHOW TO SHUT OFF THE APPLIANCE USING THE FEATURES OF YOUR FURNACEWHAT TO DO IF THE RED LAMP IS LIT Servicing Checking and Adjusting the Gas Manifold PressureChecking, Removing and Reassembling of the Vent Air Intake System Lubrication of Moving PartsAnnual Maintenance Requirements Overview Programmable TimerDay and Time Setting Setting and Adjustment Initial ConditionsProgramming the Timer Manual OperationCancelling of all Preset Programs Cancelling a Single ProgramUsing the Skip Function Skip Function Procedure During OperationTroubleshooting Step Troubleshooting Starting Sequence ElectricalStep Summer Mode StepTroubleshooting Step Starting Sequence Gas Replacement Parts Gas AssemblyElectric Box S - Combustion Blower Motor M1 - Overheat Thermostat RP8 Flame Sensor RP7 Spark Igniter 2 piecesM2 - Fan Thermostat Fan Blades 4 pieces M - Fan Motor 2 Pieces Part NumberJLTT015 Part Number JLTT023 Part Number JMTR017