Williams 1773512, 1773511 Troubleshooting Starting Sequence Electrical, Troubleshooting Step

Page 20
Troubleshooting

Troubleshooting

Starting Sequence (Electrical)

Step 1

1.Check L1 – L2 (Supply 120 V, 60 Hz)

2.Check M9 (Main fuse)

Troubleshooting Step 1

Point 1 (L1-L2)

No voltage (120 V).

Check the electrical supply line, wiring and connections.

Point 2 (M9) Fuse damaged.

Check the electrical supply line and replace the fuse.

Summer Mode

Step 2

3.Check Z1 (Reset summer/winter switch). Button down – summer mode.

4.Check Z2 (Hi-Lo flame and fan speed switch) Button down - Minimum velocity

Button up – Maximum velocity

Troubleshooting Step 2

Point 3 (Z1)

Z1 is down (closed) but there is no voltage on the fan motor M.

Check wiring and connections. If everything is okay, replace the switch.

Point 4 (Z2)

Z2 is down but the fan motor runs at the maximum velocity (120 V)

Z2 is up but the fan motor runs at the minimum velocity (lower than 120 V)

Check wiring and connections. If they are okay, replace the switch.

Winter Mode

Step 3

5.Check Z1 (Reset summer/winter switch).

Button up – winter mode.

6.Check Z3 (Manual-program mode switch).

Button up – manual mode. Button down – automatic mode.

7.Check M2 (Fan thermostat).

The thermostat is closed only when its temperature is higher than 104 °F.

19

Image 20
Contents Williams Furnace Co., 250 West Laurel Street, Colton, CA 92324 U.S.A Direct-Vent Wall FurnaceTable of Contents General Information and Technical Data Instructions to InstallerSafety Rules and General Warnings Safety Information for Users of LP GasLP Gas Warning Odor That’s your signal to go into immediate actionTechnical Data Some Points to RememberInstallation Wall InstallationFlue outlet tube length = wall thickness + 1-5/16-inches 7.9 mm Outside Location for Vent TerminalAir inlet tube length = wall thickness + 3/32-inches 2.4 mm A + 33.3 mm 13. Relocate the vent cap and attach it with the screws. Figure Gas Conversions Gas TypeNozzle Part Number Nozzle DiameterHigh Altitude Adjustment Installing a New Main Gas Shutoff ValvePressure Testing of the Gas Supply System Gas SupplyFirst Firing the Furnace Checking the Gas Inlet PressureChecking the Gas Manifold Pressure A B CElectrical Wiring Diagram Key FOR YOUR SAFETY READ BEFORE OPERATING Operating InstructionsOPERATING INSTRUCTIONS TO TURN OFF GAS TO APPLIANCEWHAT TO DO IF THE RED LAMP IS LIT HOW TO SHUT OFF THE APPLIANCEUSING THE FEATURES OF YOUR FURNACE Checking and Adjusting the Gas Manifold Pressure ServicingChecking, Removing and Reassembling of the Vent Air Intake System Lubrication of Moving PartsAnnual Maintenance Requirements Programmable Timer OverviewSetting and Adjustment Initial Conditions Day and Time SettingProgramming the Timer Manual OperationCancelling a Single Program Cancelling of all Preset ProgramsUsing the Skip Function Skip Function Procedure During OperationTroubleshooting Starting Sequence Electrical Troubleshooting StepStep Summer Mode StepTroubleshooting Step Starting Sequence Gas Electric Box Replacement PartsGas Assembly RP8 Flame Sensor RP7 Spark Igniter 2 pieces S - Combustion Blower Motor M1 - Overheat ThermostatM2 - Fan Thermostat Fan Blades 4 pieces M - Fan Motor 2 Pieces Part NumberJLTT015 Part Number JLTT023 Part Number JMTR017