9.INSTALLATION AND CONNECTION PROCEDURES
(1)System Design
Exchange/Station Configuration, Wiring Schedule and Station Numbering Schedule
(2) Equipment Installation
  | Installing the   | (See p. 13.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Installing the   | (See p. 15.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Installing the Substation  | (See p. 17.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Installing the Master Station  | (See p. 18.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
(3) Installing a Card in the   | 
  | 
  | ||
  | 
  | 
  | ||
  | Installing the Data Backup Battery  | (See p. 19.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Installing and Connecting Each Card  | (See p. 20.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
(4) Connecting the Station/Outside Line to Each Exchange Card | 
  | 
  | ||
  | 
  | 
  | ||
  | •   | (See p. 23.)  | 
  | |
  | • External Recording Device vs.   | (See p. 25.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | • Telephone vs.   | (See p. 27.)  | 
  | |
  | • External Recording Device vs.   | (See p. 29.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | • Substation vs.   | (See p. 30.)  | 
  | |
  | • External Amplifier vs.   | (See p. 31.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | • Outside Line vs.   | (See p. 32.)  | 
  | |
  | • External Recording Device vs.   | (See p. 33.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | • External Amplifier vs.   | (See p. 34.)  | 
  | |
  | • External Recording Device vs.   | (See p. 35.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | (See p. 39.)  | 
  | ||
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
(5)   | 
  | 
  | ||
  | 
  | 
  | ||
  | (See p. 36.)  | 
  | ||
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
(6) Connecting the   | 
  | 
  | ||
  | 
  | 
  | ||
  | Connection to a Programming PC  | (See p. 40.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Connection to an Operation Log PC  | (See p. 42.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | Power  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
(7) Adjusting the Station and Exchange | 
  | 
  | ||
  | 
  | 
  | 
  | |
  | System Programming (See the   | 
  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Master Station Microphone Sensitivity/Speaker Volume Adjustment  | (See p. 26.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Telephone Volume Adjustment   | (See p. 28.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
(8) Speech and Function Tests  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Speech Test  | (See p. 44.)  | 
  | |
  | 
  | 
  | 
  | |
  | 
  | 
  | ||
  | Function Test  | (See p. 44.)  | 
  | |
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
12