Weil-McLain EGH-125, EGH-105 manual Replace pilot assembly

Page 27

CSD-1 control system — Natural gas

VIII Check-out procedure — troubleshooting

TS-1: No Spark — System (boiler without vent damper) does not work

Correct by making connections.

Check for open thermostat, circulator relay, operating control, limit control or LWCO. Check the CSD-1 control panel, impulse relay and push-button switch.

If limit controls or water level controls lockout on manual reset, determine cause and correct condition. Failure to do so could result in severe personal injury, death or substantial property damage.

Replace ignition control. Retest.

Securely connect spark wire. Then turn ON supply voltage. Retest.

Replace pilot assembly. Retest.

Is spark gap 0.125" and isolated in pilot gas stream?

 

No

 

Yes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Replace pilot assembly,

 

 

 

 

 

turn ON supply voltage.

 

 

 

 

 

 

 

 

 

 

Operate system several

 

 

Replace ignition

 

complete heat cycles.

 

 

 

 

 

control. Retest.

 

 

 

 

 

 

 

 

 

 

 

 

Part Number 550-110-677/0299

 

 

VISUALLY CHECK — Is ground wire connected from GND (Burner) to ignition control mounting screw, and ground wire connected from transformer terminal C to case ground?

No

Yes

 

 

 

 

 

 

Is 24VAC present across terminals 24V and 24V(GND)?

 

No

Yes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Open thermostat (or operating control) contacts for 15 seconds. Close thermostat contacts. Is 24VAC across terminals PV & MV/PV?

No

Yes

 

 

 

Turn OFF supply voltage.

Electrical shock hazard. Failure to turn off power before proceeding could cause severe personal injury or death.

Check spark wire. Is it securely connected to spark transformer?

No

Yes

 

 

 

 

 

 

Is condition of spark wire good (not cut, brittle, burned or cracked)?

No

Yes

 

 

 

Is spark electrode ceramic cracked?

No

Yes

 

 

 

 

 

 

Replace pilot assembly, turn ON supply voltage, operate system several complete heat cycles.

27

Image 27
Contents Control Supplement Please read this page first Boiler cartons Carton guideGas train assembly InstallationVent damper assemblies Install optional vent damper if suppliedIII Install boiler controls water boilers II Piping connectionsWater boiler connections III Install boiler controls steam boilers IV Optional heaters steam boilers onlySteam boiler connections Gas piping VI WiringCall for heat VI Wiring sequence of operationWater boiler wiring Wiring water boilersSchematic Wiring Diagram Control assembly water boiler VI Wiring water boilersCSD-1 control panel Gravity return VI Wiring steamSchematic Wiring Diagram 13a Control assembly steam, gravity returnCSD-1 control panel Pumped return Schematic Wiring Diagram Control assembly steam, pumped return Terminal strip Before proceeding To place boiler in operation VII Final adjustmentsOperating instructions VII Final adjustments operating instructionsViii Check-out procedure operation Leak test procedure Viii Check-out procedure leak testVerify proper operation after servicing Viii Check-out procedure troubleshootingReplace pilot assembly TS-2 No Spark System boiler with vent damper does not work Not OK TS-3 Pilot lights Main valve will not come on from previous IX Service and maintenance Water boiler assembly Replacement parts water boilersRV20VL Water boiler replacement partsSteam boiler assembly Replacement parts steam boilersRV20VL Steam boiler replacement partsWeil-McLain Blaine Street Michigan City,