Weil-McLain 550-141-829/1201 manual Before Installing Boiler, Installations must comply with

Page 4

Before Installing Boiler

Installations must comply with:

U.S.

State and local plumbing, heating and electrical codes.

National codes where applicable.

Canada

Canadian Standards Association, CSA B139, Installation Code for Oil-Burning Equipment.

CSA C22.1 Canadian Electrical Code Part One.

Applicable local or provincial codes.

Before selecting boiler location:

Check for nearby connections to:

System water piping.

Chimney. See pages 12-13. Boiler can be top or back vented.

Combustion and ventilation air supply. See page 5.

Oil supply. See page 24 for oil line routing.

Electrical power.

Check area around boiler. Remove any combustible materials, gasoline and other flammable liquids.

Failure to keep boiler area clear and free of combustible

materials, gasoline and other flammable liquids and vapors can result in severe personal injury, death or substantial property damage.

Provide clearances around boiler (see FIGURE 1):

Jacket cap must be in place on boiler to avoid requiring an 18"

minimum clearance from back or top of boiler to combustible material.

Minimum clearances from vent pipe to combustible material:

6 inches — Type “L” doublewall vent*

18 inches — Singlewall vent*

Flue pipe clearances must take precedence over jacket clearances.

Recommended service clearances:

24 inches — Front and top

6 inches — Left side**, back and right side Δ 15 inches — Left side with tankless heater**

12 inches — Right side for burner door swing radius Δ

Recommended Service Clearances

FIGURE 1

4

Image 4
Contents This Manual Includes Installation Start-Up Boiler Parts Symbol Definitions When Calling or Writing About the BoilerRead This Page First Hazard DefinitionsTable of Contents Before Installing Boiler Installations must comply withBefore selecting boiler location Provide clearances around boiler see FigureProvide air for combustion and ventilation Lay a foundation, if neededInstall Packaged Boiler Place boilerTankless heater, if used Perform hydrostatic pressure testInstall Non-Packaged Boiler Fiberglass wool and ceramic fiber materialsNon-Packaged SGO-3 through 6 position on site Install Non-Packaged Boiler Install Packaged and Non-Packaged Boiler Install burner also refer to instructions packed with burnerInstall Packaged and Non-Packaged Boiler Connect Breeching General chimney requirementsConnect Breeching Connect Steam Piping Install pipingGeneral piping information Connect Steam Piping Connect Steam Piping Optional reservoir piping Condensate Receiver Capacity TableConnect Tankless Heater Piping To pipe tankless heaterConnect Wiring General wiring requirementsThermostat wiring Burner wiringConnect Wiring Low Water Cutoff Wiring Harness not furnished on a Boilers Connect Wiring Boiler Wiring for Probe-Type Lwco General oil piping requirements Connect Oil PipingOil piping connection at burner Start-Up Fill the systemTips for steam systems To place in operationCheck-Out Procedure Check off steps as completedAppendix Burner adjustments for P and a boilersTo connect SGO boilers to indirect-fired water heaters Parts List Parts Drawing Dimensions DimensionsDimensions