Minimum Runtime |
| Minimum Runtime: |
Options: 1 to 60 minutes | Default: 2 minutes | 2m |
SET /<Settings>/<Stage>/Min. Runtime |
|
|
•This is the minimum amount of time any stage will run.
•The Minimum Runtime for the lowest firing stage on a boiler starts after the purge cycle.
•Initially, set the Min. Runtime to half the Reaction Time.
•If System tends to overshoot, reduce the Min. Runtime. If boilers tend to short cycle, increase the Min. Runtime.
Lead Boiler (Not Available for Lo/Hi or | Lead Boiler: | |
Options: Output 1, Output 2, or Output 3 | Default: Output 1 | Output 1 |
SET /<Settings>/<Stage>/Lead
•The Lead boiler will always be the first boiler brought on when there is a call for output. As more heat is needed, additional boilers are added.
Lead Rotation (Not Available for Lo/Hi or
Lead Rotation Options: Manual or Time | Default: Time | |
Rotation Period Options: 1 to 999 Hours | Default: 24 Hours | |
SET | /<Settings>/<Stage>/Lead |
|
SET | /<Settings>/<Stage>/Lead/Rotate |
|
•The Lead boiler can be rotated automatically based on time or manually. The Time rotation is recommended for most applications.
• If Time is selected, a second screen will allow the adjustment of the Auto Rotate Period If 24 Hours (default setting) was selected, the first rotation will take effect after 12 hours. The following rotations will take place every 24 hours thereafter.
•If Manual Lead Rotation is selected, it will be followed by the Lead Boiler selection option. (See previous topic.)
Lead Rotation:
Time
Manual
Rotation Period: 24hrs
Single On/Off Boiler and System Pump Settings
Differential (Available for |
| Differential: |
Options: From 1ºF/1ºC to 20ºF/11ºC | Default: 5ºF/3ºC | 5 F |
SET /<Settings>/Diff.
•The Differential controls boiler cycling. When there is a call for heat, the boiler will be activated until the Calculated temperature is reached. The boiler will then turn off and stay off until the system water temperature falls to the Set Point less the Differential.
•A smaller Differential setting will normally result in tighter control of the set point but will tend to increase the frequency of boiler cycling. Larger Differential values will reduce boiler short cycling, but the system will be allowed to vary further from the target value.
|
| Pump |
Options: From 0 min to 60 min | Default: 2 min | 2m |
SET /<Settings>/Run On
•The System Pump relay will energize whenever the Outdoor temperature is below the Outdoor Cutoff. When the Outdoor temperature increases 2°F above the Outdoor Cutoff and after the boiler relay has
•The
•When DHW Priority is selected while the EXT+/EXT- (Enable/Disable terminals) are open or the outdoor temperature is above the Outdoor Cutoff, a DHW call will energize only the DHW relay. When the DHW call expires, the DHW Pump relay will run for the
12