4d Piping — low temperature systems

SYSTEM-bypass piping method

This piping method is called a system-bypassbecause part of the circulator flow bypasses the system (through valve 7a). This bypassed hot water from the boiler outlet mixes with cooler system return water temperature in order to provide minimum 130°F return water to the boiler. Valve 7b will most often be full open, but may need to be slightly closed on some low pressure drop sys- tems in order to cause enough flow through valve 7a.

Figure 24 is an alternative piping method that provides return water temperature control for boilers installed on converted gravity systems (large water content or steam systems).

Do not apply the piping of Figure 24 on radiant heat- ing systems. It provides no method regulating the water temperature provided to the system and could result in excessive water temperature in the radiant tubing.

System-bypass piping as shown in Figure 24 can be used with either zone valve or circulator zoning. When used with circulator zoning however, the boiler circulator (item 3), must be piped as shown. It cannot be used as one of the zoning circulators.

Do not apply system-bypass piping if the reduced flow in the system could cause poor heat distribution. That is, system-bypass piping reduces the flow in the system and increases the water temperature supplied to the system. This can cause increased heat from radiators at the beginning of the system and reduced heat from radiators near the end of the system.

Valve adjustment

1.Start with valve 7a fully closed and 7b fully open.

2.Gradually open valve 7a while closing valve 7b until the temperature at gauge 8 reads at least 130°F at all times.

3.Valve 7a regulates the amount of boiler supply water mixed with return water. Valve 7b causes a pressure drop in the system needed to balance flow through valve 7a and the system.

4.The valve adjustment should be done with the system at the coldest expected temperature (60°F for converted gravity systems or high mass radiant systems).

Failure to prevent low return water temperature to the boiler could cause corrosion of the boiler sections or burners, resulting in severe personal injury, death or substantial property damage.

Radiant heating system piping should include a means of regulating the boiler return water temperature and the system supply temperature (such as provided by an injec- tion pumping control).

Boiler return water temperature will be adequately controlled using the methods shown in this manual provided the system supply temperature is relatively constant.

DO NOT apply the methods of this manual if the system is equipped with an outdoor reset control. Instead, provide controls and piping which can regulate the boiler re- turn water temperature at no less than 130°F regardless of system supply temperature. Contact your Weil-McLain representative for suggested piping and control methods.

Failure to prevent cold return water temperature to the boiler could cause corrosion damage to the sections or burners, resulting in possible severe personal injury, death or substantial property damage.

28

Part Number 550-110-710/0107

 

Image 28
Contents Gold CGi How it works Gold CGi Gas-Fired Induced-Draft Water Boiler Contents Please read before proceeding Installations must follow these codes 1a Prepare boiler location codes & checklistBefore locating the boiler, check the following 1b Prepare boiler location clearances 1c Prepare boiler location vent system When removing boiler from an existing common vent systemChimney or vent require- ments 1d Prepare boiler location air contamination Products to avoid1e Prepare boiler location air openings Air openings must be providedAir opening options Two openings Air supply from inside the buildingExhaust fans and air movers Motorized air dampersSingle air opening option Exception for large spaces2a Prepare boiler placement & setup Orifice replacement procedurePlace boiler/crate near position Inspect orifices and burners2b Prepare boiler pressure test Hydrostatic pressure testDrain and remove fittings Prepare boiler for test3a Venting general information Venting chimney draft ventingCGi venting methods Chimney draft or Direct exhaust Chimney draft venting3c Venting Direct exhaust components Obtain vent system components3d Venting direct exhaust vent starter Vent StaR-34 Vent starter3e Venting direct exhaust termination Vent termination minimum clearancesVertical venting See . Follow vent 3f Venting direct exhaust installationSidewall venting See Figures 14 Using any termination other than one of those shown 4a Water piping general information Diaphragm-type or bladder- type expansion tank Figure 4b Water piping single-zone systemClosed-type expansion tank 4c Water piping multiple zones Piping multiple zonesZoning with circulators 4d Piping low temperature systems Temperature gaugesValve adjustment Primary/secondary preferred bypass piping methodPrimary/secondary piping Valve adjustment BOILER-bypass piping methodBoiler-bypass piping Zoning with SYSTEM-bypass piping method 4e Water piping refrigeration system Prevent chilled water from entering boilerConnecting gas supply piping to boiler Gas pipingNatural Gas Propane GasField wiring Electrical installation must comply withWiring connections ThermostatFreeze protection when used 7a Start-up preparationCheck for gas leaks Determine if water treatment is neededDo not use petroleum-based cleaning or sealing compounds Fill the system with waterInspect system water piping Inspect base insulationStart the boiler 7b Start-up operate boilerCheck system and boiler 7c Start-up if boiler doesn’t start Check burner flamesCheck for Pilot burner flame FigureCheck-out procedure checklist Thermostats9a Operation sequence During main burner operation9b Operation wiring diagrams Schematic wiring diagramLadder wiring diagram 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-8 10a Service and maintenance schedule Verify Proper Operation After Servicing10b Service and maintenance annual start-up 10b Service & maintenance annual start-up Burners and baseCondensate drain system Inducer motorGas piping Cold fill and operating pressuresAir vents and air elimination Limit controls and cutoffsBoiler relief valve Review with ownerReview the User’s Information Manual with the owner 11a Troubleshooting procedure 11b Troubleshooting componentsBefore troubleshooting Air pressure switchControl indicator lights Troubleshooting the control moduleControl indicator lights Lockout modes Control moduleControl module connections 11c Troubleshooting control module lights Chart Light flashingRemove 120 VAC in plug , Item 3, page 50 on control module VAC in plugChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Chart 4 Flame & Power lights flashing Usually indicates flame sensed when it shouldnt be thereDoes blower motor operate? Item 8 , Verify Sequence Operation, FigureSection assembly Base Jacket Trim Controls 12a Replacement partsControls Repair Parts Lists 12b Replacement parts section assembly Section assembly12c Replacement parts base Base assemblyDescription Weil-McLain Part number 12d Replacement parts jacket Jacket assemblyModel Weil-McLain part number BoilerBoiler Model Weil-McLain part number 12e Replacement parts trim Fittings shown are included with boiler12f Replacement parts controls Propane gas components13a Dimensions Dimensional drawing13b Ratings Handling ceramic fiber and fiberglass materials Removal of Combustion Chamber Lining or Base Panels