Weil-McLain 550-110-710/0107 manual Fill the system with water, Inspect system water piping

Page 33

GOLD CGi Gas-Fired Water Boiler — Boiler Manual

7a Start-up — preparation (continued)

Fill the system with water

1.Close manual and automatic air vents and boiler drain cock.

2.Fill to correct system pressure. Correct pressure will vary with each application. Typical cold water fill pressure for a residential system is 12 psi.

3.Purge air from system:

a.Connect a hose to the purge valve (see drain valves, item 6, in suggested piping diagrams on pages 23 through 27, Figure 18 through Figure 23). Route hose to an area where water can drain and be seen.

b.Close the boiler or system isolation valve between the purge valve and fill connection to the system.

c.Close zone isolation valves.

d.Open quick-fill valve on cold water makeup line.

e.Open purge valve.

f.One zone at a time, open the isolation valves. Allow water to run through the zone, pushing out the air. Run until no noticeable air flow is present. Close the zone isolation valves and proceed with the next zone. Follow this procedure until all zones are purged.

g.Close the quick-fill water valve and purge valve and remove the hose. Open all isolation valves. Watch that system pressure rises to correct cold-fill pressure.

h.After the system has operated for a while, eliminate any residual air by using the manual air vents located throughout the system.

i.If purge valves are not installed in system, open manual air vents in system one at a time, beginning with lowest floor. Close vent when water squirts out. Repeat with remaining vents.

4.Open automatic air vent (diaphragm-type or bladder-type expansion tank systems only) one turn.

Inspect system water piping

After filling the boiler and system with water, inspect all piping throughout the system for leaks. If found, repair immediately. Repeat this inspection after the boiler has been started and the system has heated up.

Leaks must be repaired at once.

Failure to do so can damage the boiler, resulting in substantial prop- erty damage.

Do not use petroleum-based cleaning or sealing compounds

in boiler system. Severe damage to boiler will occur, resulting in sub- stantial property damage.

Inspect base insulation

The boiler contains ceramic fiber and fiberglass materials. Use care when handling these materials per instructions on page 68 of this manual. Failure to comply could result in severe personal injury.

Failure to replace damaged insu-

lation or reposition insulation can result in a fire hazard, causing severe personal injury, death or substantial

5.Open other vents:

a.Starting on the lowest floor, open air vents one at a time until water squirts out.

b.Repeat with remaining vents.

6.Refill to correct pressure.

property damage.

Check to make sure base insulation is secure against all four sides of the base. If insulation is damaged or displaced, do not operate boiler. Replace or reposition insulation.

Part Number 550-110-710/0107

33

 

Image 33
Contents Gold CGi How it works Gold CGi Gas-Fired Induced-Draft Water Boiler Contents Please read before proceeding 1a Prepare boiler location codes & checklist Installations must follow these codesBefore locating the boiler, check the following 1b Prepare boiler location clearances When removing boiler from an existing common vent system 1c Prepare boiler location vent systemChimney or vent require- ments Products to avoid 1d Prepare boiler location air contaminationAir openings must be provided 1e Prepare boiler location air openingsAir opening options Two openings Air supply from inside the buildingMotorized air dampers Exhaust fans and air moversSingle air opening option Exception for large spacesOrifice replacement procedure 2a Prepare boiler placement & setupPlace boiler/crate near position Inspect orifices and burnersHydrostatic pressure test 2b Prepare boiler pressure testDrain and remove fittings Prepare boiler for testVenting chimney draft venting 3a Venting general informationCGi venting methods Chimney draft or Direct exhaust Chimney draft ventingObtain vent system components 3c Venting Direct exhaust componentsVent StaR-34 Vent starter 3d Venting direct exhaust vent starterVent termination minimum clearances 3e Venting direct exhaust termination3f Venting direct exhaust installation Vertical venting See . Follow ventSidewall venting See Figures 14 Using any termination other than one of those shown 4a Water piping general information 4b Water piping single-zone system Diaphragm-type or bladder- type expansion tank FigureClosed-type expansion tank Piping multiple zones 4c Water piping multiple zonesZoning with circulators Temperature gauges 4d Piping low temperature systemsValve adjustment Primary/secondary preferred bypass piping methodPrimary/secondary piping BOILER-bypass piping method Valve adjustmentBoiler-bypass piping Zoning with SYSTEM-bypass piping method Prevent chilled water from entering boiler 4e Water piping refrigeration systemGas piping Connecting gas supply piping to boilerNatural Gas Propane GasElectrical installation must comply with Field wiringWiring connections Thermostat7a Start-up preparation Freeze protection when usedCheck for gas leaks Determine if water treatment is neededFill the system with water Do not use petroleum-based cleaning or sealing compoundsInspect system water piping Inspect base insulation7b Start-up operate boiler Start the boilerCheck system and boiler Check burner flames 7c Start-up if boiler doesn’t startCheck for Pilot burner flame FigureThermostats Check-out procedure checklistDuring main burner operation 9a Operation sequenceSchematic wiring diagram 9b Operation wiring diagramsLadder wiring diagram 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-8 Verify Proper Operation After Servicing 10a Service and maintenance schedule10b Service and maintenance annual start-up Burners and base 10b Service & maintenance annual start-upCondensate drain system Inducer motorCold fill and operating pressures Gas pipingAir vents and air elimination Limit controls and cutoffsReview with owner Boiler relief valveReview the User’s Information Manual with the owner 11b Troubleshooting components 11a Troubleshooting procedureBefore troubleshooting Air pressure switchTroubleshooting the control module Control indicator lightsControl indicator lights Lockout modes Control moduleControl module connections Chart Light flashing 11c Troubleshooting control module lightsRemove 120 VAC in plug , Item 3, page 50 on control module VAC in plugChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Usually indicates flame sensed when it shouldnt be there Chart 4 Flame & Power lights flashingDoes blower motor operate? Item 8 , Operation, Figure Verify Sequence12a Replacement parts Section assembly Base Jacket Trim ControlsControls Repair Parts Lists Section assembly 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Model Weil-McLain part numberBoiler Model Weil-McLain part number Fittings shown are included with boiler 12e Replacement parts trimPropane gas components 12f Replacement parts controlsDimensional drawing 13a Dimensions13b Ratings Removal of Combustion Chamber Lining or Base Panels Handling ceramic fiber and fiberglass materials