Weil-McLain 550-110-710/0107 manual Please read before proceeding

Page 5

GOLD CGi Gas-Fired Water Boiler — Boiler Manual

Please read before proceeding

Installer

Read all instructions before in- stalling. Follow all instructions in proper order to prevent personal injury or death.

Consider piping and installation when determining boiler location.

Any claims for damage or shortage in shipment must be filed immediately against the transportation company by the consignee.

User

This manual is for use only by your qualified heating installer/service technician.

Please refer to the User’s Information Manual for your reference.

We recommend regular service by a qualified service technician, at least annually.

The boiler contains ceramic fiber and fiberglass materials. Use care when handling these materials per instructions on page 68 of this manual. Failure to comply could result in severe personal injury.

When calling or writing about the boiler— Please have the boiler model number from the boiler rating label and the CP number from the boiler jacket. You may list the CP number in the space provided on the Installation and service certificate found on page 36.

Failure to adhere to the guidelines on this page can result in severe personal injury, death or substantial property damage.

When servicing boiler —

To avoid electric shock, disconnect electrical supply before performing maintenance.

To avoid severe burns, allow boiler to cool before performing maintenance.

Boiler operation —

Do not block flow of combustion or ventilation air to boiler.

Should overheating occur or gas supply fail to shut off, do not turn off or disconnect electrical supply to circulator. Instead, shut off the gas supply at a location external to the appliance.

Do not use this boiler if any part has been under water. Immediately call a qualified service technician to inspect the boiler and to replace any part of the control system and any gas control that has been under water.

Boiler water —

Do not use petroleum-based cleaning or sealing compounds in boiler system. Water seal deterioration will occur, causing leakage between sections. This can result in substantial property damage.

Do not use “homemade cures” or “boiler patent medicines”. Serious damage to boiler, personnel and/or property may result.

Continual fresh makeup water will reduce boiler life. Mineral buildup in sections re- duces heat transfer, overheats cast iron, and causes section failure. Addition of oxygen and other gases can cause internal corrosion. Leaks in boiler or piping must be repaired at once to prevent makeup water.

Do not add cold water to hot boiler. Thermal shock can cause sections to crack.

Glycol — potential fire hazard —

All glycol is flammable when exposed to high temperatures. If glycol is allowed to accumulate in or around the boiler or any other potential ignition source, a fire can develop. In order to prevent potential severe personal injury, death or substantial property damage from fire and/or structural damage:

Never store glycol of any kind near the boiler or any potential ignition source.

Monitor and inspect the system and boiler regularly for leakage. Repair any leaks im- mediately to prevent possible accumulation of glycol.

Never use automotive antifreeze or ethylene glycol in the system. Using these glycols can lead to hazardous leakage of glycol in the boiler system.

Part Number 550-110-710/0107

Image 5
Contents Gold CGi How it works Gold CGi Gas-Fired Induced-Draft Water Boiler Contents Please read before proceeding Before locating the boiler, check the following 1a Prepare boiler location codes & checklistInstallations must follow these codes 1b Prepare boiler location clearances Chimney or vent require- ments When removing boiler from an existing common vent system1c Prepare boiler location vent system Products to avoid 1d Prepare boiler location air contaminationAir openings must be provided 1e Prepare boiler location air openingsAir opening options Two openings Air supply from inside the buildingMotorized air dampers Exhaust fans and air moversSingle air opening option Exception for large spacesOrifice replacement procedure 2a Prepare boiler placement & setupPlace boiler/crate near position Inspect orifices and burnersHydrostatic pressure test 2b Prepare boiler pressure testDrain and remove fittings Prepare boiler for testVenting chimney draft venting 3a Venting general informationCGi venting methods Chimney draft or Direct exhaust Chimney draft ventingObtain vent system components 3c Venting Direct exhaust componentsVent StaR-34 Vent starter 3d Venting direct exhaust vent starterVent termination minimum clearances 3e Venting direct exhaust terminationSidewall venting See Figures 14 3f Venting direct exhaust installationVertical venting See . Follow vent Using any termination other than one of those shown 4a Water piping general information Closed-type expansion tank 4b Water piping single-zone systemDiaphragm-type or bladder- type expansion tank Figure Piping multiple zones 4c Water piping multiple zonesZoning with circulators Temperature gauges 4d Piping low temperature systemsValve adjustment Primary/secondary preferred bypass piping methodPrimary/secondary piping BOILER-bypass piping method Valve adjustmentBoiler-bypass piping Zoning with SYSTEM-bypass piping method Prevent chilled water from entering boiler 4e Water piping refrigeration systemGas piping Connecting gas supply piping to boilerNatural Gas Propane GasElectrical installation must comply with Field wiringWiring connections Thermostat7a Start-up preparation Freeze protection when usedCheck for gas leaks Determine if water treatment is neededFill the system with water Do not use petroleum-based cleaning or sealing compoundsInspect system water piping Inspect base insulationCheck system and boiler 7b Start-up operate boilerStart the boiler Check burner flames 7c Start-up if boiler doesn’t startCheck for Pilot burner flame FigureThermostats Check-out procedure checklistDuring main burner operation 9a Operation sequenceSchematic wiring diagram 9b Operation wiring diagramsLadder wiring diagram 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-6 9c Operating instructions CGi-25 to CGi-8 Verify Proper Operation After Servicing 10a Service and maintenance schedule10b Service and maintenance annual start-up Burners and base 10b Service & maintenance annual start-upCondensate drain system Inducer motorCold fill and operating pressures Gas pipingAir vents and air elimination Limit controls and cutoffsReview the User’s Information Manual with the owner Review with ownerBoiler relief valve 11b Troubleshooting components 11a Troubleshooting procedureBefore troubleshooting Air pressure switchTroubleshooting the control module Control indicator lightsControl indicator lights Lockout modes Control moduleControl module connections Chart Light flashing 11c Troubleshooting control module lightsRemove 120 VAC in plug , Item 3, page 50 on control module VAC in plugChart 2 Tstat Circ & Power lights flashing Chart 3 Press Switch & Power lights flashing Usually indicates flame sensed when it shouldnt be there Chart 4 Flame & Power lights flashingDoes blower motor operate? Item 8 , Operation, Figure Verify SequenceControls Repair Parts Lists 12a Replacement partsSection assembly Base Jacket Trim Controls Section assembly 12b Replacement parts section assemblyBase assembly 12c Replacement parts baseDescription Weil-McLain Part number Jacket assembly 12d Replacement parts jacketBoiler Model Weil-McLain part number BoilerModel Weil-McLain part number Fittings shown are included with boiler 12e Replacement parts trimPropane gas components 12f Replacement parts controlsDimensional drawing 13a Dimensions13b Ratings Removal of Combustion Chamber Lining or Base Panels Handling ceramic fiber and fiberglass materials