Burnham LEDV SERIES III. Water Piping and Trim, Design and install boiler and system piping to

Page 9

III. Water Piping and Trim

A. Design and install boiler and system piping to

prevent oxygen contamination of boiler water.

There are many possible causes of oxygen contamination such as:

1.Addition of excessive make-up water as a result of system leaks.

2.Absorption through open tanks and fittings.

3.Oxygen permeable materials in the distribution system.

In order to insure long product life, oxygen sources should be eliminated. This can be accomplished by taking the following measures:

1.Repairing system leaks to eliminate the need for addition of make-up water.

2.Eliminating open tanks from the system.

3.Eliminating and/or repairing fittings which allow oxygen absorption.

4.Use of non-permeable materials in the distribution system.

5.Isolating the boiler from the system water by installing a heat exchanger.

B.Connect System supply and return piping to boiler. See Figures 5 and 7. Also consult I=B=R Installation and Piping Guides. Maintain minimum ½ inch clearance from hot water piping to combustible materials.

1.If this boiler is used in connection with refrigeration systems, the boiler must be installed so that the chilled medium is piped in parallel with the heating boiler using appropriate valves to prevent the chilled medium from entering the boiler, see Figure 6. Also consult I=B=R Installation and Piping Guides.

2.If this boiler is connected to heating coils located in air handling units where they may be exposed to

refrigerated air, the boiler piping must be equipped with flow control valves to prevent gravity circulation of boiler water during the operation of the cooling system.

3.If boiler is used with an Alliance Indirect-Fired Domestic Water Heater, install the Alliance as a separate heating zone. Refer to the Alliance Installation, Operating, and Service Instructions for additional information.

4.Use a system bypass if the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperatures may be encountered (i.e. converted gravity circulation system, etc.).

The bypass should be the same size as the supply and return lines with valves located in the bypass and return line as illustrated in Figures 5 and 7 in order to regulate water flow for maintenance of higher boiler water temperature.

Set the by-pass and return valves to a half throttle position to start. Operate boiler until the system water temperature reaches its normal operating range.

Adjust the valves to maintain 180°F to 200°F boiler water temperature and greater than 120°F return temperature. Adjust both valves simultaneously. Closing the boiler return valve while opening the by- pass valve will raise the boiler return temperature. Opening the boiler return valve while closing the by- pass valve will lower the boiler return temperature.

5.A hot water boiler installed above radiation level must be provided with a low water cutoff device as part of the installation.

C.Install Safety Relief Valve. See Figures 5 and 7. Safety Relief Valve must be installed with spindle in vertical position. Installation of the relief valve must be consistent with the ANSI/ASME Boiler and Pressure Vessel Code, Section IV.

WARNING

Safety (relief) valve discharge piping must be piped near floor to eliminate potential of severe burns. Do not pipe in any area where freezing could occur. Do not install any shut- off valves, plugs or caps.

9

Image 9 Contents
81433101R3-3/00 Important Information Please Read this page Carefully Page USA Boilers Table of Contents Pre-Installation II. Unpack Boiler Install Boiler ControlRemove Crate Removal of Boiler from SkidProper Hinge Bracket Installation III. Water Piping and Trim Design and install boiler and system piping toRecommended Boiler Piping for Zoning with Valves Recommended Boiler Piping for Zoning with Circulators General Guidelines IV. Venting / Air Intake PipingDirect Oil Vent Pipe Pipe Length Burnham Part No Vent Installation Vent Connector, Assembled Air Intake Installation Direct Vent only See Figure Page Electrical and Sequence of Operations ElectricalSequence of Operations Schematic Wiring Diagram VI. Oil Piping GeneralSingle-pipe Oil Lines Two-Pipe Oil Lines Two-Pipe InstallationVII. System Start-up Alwaysinspectinstallationbefore Starting BurnerBURNERSTART-UP Remove Test Plug in Flue CollarHints on Combustion Adjust OIL PressureTest Controls Simulate power failure For Heating Serviceman onlySimulate flame failure Simulate ignition failureSection Viii Service and Cleaning Firetubes and Combustion ChamberBurner Low water cutoff if so equipped Service Notes Urnham Corporation Regional Offices IX. Repair PartsLedv Boiler Trim & Controls Ledv Boiler Jacket & Insulation Ledv Bare Boiler Assembly PartsRepair KitVent 22Figure Beckett Afii Oil Burner Repair Part LEDV1 LEDV2 LEDV3