A.O. Smith 1500, 200, 201, 2500 Horizontal Vent Installation, Standard Vertical VENTING, Category

Page 14

STANDARD (VERTICAL) VENTING, CATEGORY I

THIS BOILER MAY BE VENTED ACCORDING TO TABLE 7 (ALSO SEE FIGURE 5). AT LEAST TYPE B VENTING MUST BE USED WITH THE STANDARD VENTING OPTION (thru-the-roof) USING THE NATIONAL FUEL GAS CODE VENT TABLES.* TYPE B VENT PIPE CANNOT BE USED IF THE BOILER IS VENTED HORIZONTALLY OR AS A DIRECT VENT (SEE PAGES 11 THROUGH 13). ALL LOCAL UTILITY, STATE/ PROVINCIAL, REGULATIONS ON VENTING MUST BE FOLLOWED.

VENT SIZING, INSTALLATION AND TERMINATION SHALL BE IN ACCORDANCE WITH THE NATIONAL FUEL GAS CODE, ANSI Z223.1 OR CAN/CSA-B149.1 and .2 (AND LATEST ADDENDA).*

Vent connections must be made to an adequate stack or chimney and shall be in accordance with the National Fuel Gas Code, ANSI Z223.1 or CAN/CSA-B149.1and .2 (and latest addenda) or applicable provisions of the local building codes. Size and install proper size vent pipe.

Horizontal runs of vent pipe shall be securely supported by adequately placed (approximately every 4 feet [1.2 m]), noncombustible hangers suitable for the weight and design of the materials employed to prevent sagging and to maintain a minimum upward slope of 1/4" per foot (2 cm/m) from the boiler to the vent terminals. Dampers or other obstructions must not be installed in the vent. Be sure that the vent connector does not extend beyond the inside wall of the chimney.

Table 11: VENT CONNECTION

VENT CONNECTOR

MODEL NUMBER

G(W,B) 1000

10" (25.4 cm)

G(W,B) 1300

12" (30.5 cm)

G(W,B) 1500

12" (30.5 cm)

G(W,B) 1850

14" (35.6 cm)

G(W,B) 2100

14" (35.6 cm)

G(W,B) 2500

16" (40.6 cm)

 

 

For vent arrangements other than table 7 and for proper boiler operation, a barometric damper is required to maintain draft between -0.02" W.C.. and -0.04" W.C. at 2 feet (0.6 m) above the boiler vent collar.

STANDARD (HORIZONTAL) VENTING, CATEGORY III

Vent sizing, installation and termination shall be in accordance with the NATIONAL FUEL GAS CODE, ANSI Z223.1 OR CAN/CSA-B149.1 AND .2 (LATEST EDITIONS). If applicable, all local, utility, state/provincial regulations on venting must be followed. See table 8 for venting specifications. The exhaust vent pipe must be of a type listed for use with Category III gas burning heaters such as "Saf-T-Vent" manufactured by Heat-Fab Inc.

For Category III installations, It is important that the Installed vent be airtight. Please insure that all joints are sealed properly during installation.

DIRECT VENT VERTICALAND HORIZONTAL VENTING

For direct vent applications this boiler may be vented according to tables 9 and 10. For category III applications, the exhaust vent pipe must be special gas vent pipe listed for use with category III gas burning heaters such as "Saf-T-Vent" manufactured by Heat-Fab Inc. This vent system must be 100% sealed with a condensate trap located as close to the boiler as possible.

When sizing exhaust piping and intake air piping, 90-degree elbows are equivalent to 10 feet (3.1 m) of straight pipe and 45-degree elbows are equal to 5 feet (1.5 m) of straight pipe.

The intake air piping can be PVC, CPVC, ABS or any suitable intake air piping that can be sealed.

Combustion air from outside the building ducted to boiler air inlet (Ducted Air Application) cannot be used in rooms with negative pressure.

HORIZONTAL VENT INSTALLATION

This boiler can be vented through the rear of the cabinet with the use of the Fluebox and vent adaptor. Any of the previous venting configurations can be installed with rear connections.

To change the unit to rear exhaust:

1.The vent collar and cover plates must be removed from the top and rear of the unit.

2.Trim the insulation from around the rear flue hole in the jacket and the fluebox. Support insulation from inside the fluebox to facilitate cutting. Use safety precautions such as gloves. Place the gasket and vent adaptor in the horizontal position. Place the gasket and flue plate in the vertical position as shown in figure 9.

Figure 9. Switching from Vertical to Horizontal Venting

14

Image 14
Contents For buying this cost efficient, high recovery unit from Limited WarrantyRough in Dimensions ROUGH-IN DimensionsGAS and Electrical Characteristics Recovery Capacities Heat Exchanger Pressure DropGrounding Instructions High Altitude InstallationForeword Correct GASFEATURES/CONTROLS Circulating Pump Installation InstructionsSafety Relief Valves Required AbilityLevelling Installation ClearancesChemical Vapor Corrosion AIR RequirementsUnconfined Space Connecting Boiler to a Common VentVenting Confined SpaceIntake/Exhaust Installation Requirements See figure Location Requirements INTAKE/EXHAUSTEquivalent Standard Vent Vertical CategoryType B or 16 40.6 cmIII Stainless Standard Vent Horizontal CategoryVenting Vent Size Vent Length Material Inches Feet SteelDirect Vent Vertical Exhaust Configurations Direct Vent Vertical CategoryDirect Vent Horizontal Exhaust Configurations Direct Vent Horizontal CategoryStandard Vertical VENTING, Category Horizontal Vent InstallationVent Connector Model Number Standard Horizontal VENTING, CategorySystem Installation Hydronic InstallationCooling Piping Space Heating ApplicationsHOT Water Supply Boiler Installation Single boiler with horizontal tank Single boiler with vertical tank Suggested Pipe Size For Multiple Gas Appliances Propane Gas Distance from Meter BTU Input Single Unit INSTALLATION, Suggested Pipe SizeGAS Connections BtuhFilling for HOT Water Supply Boiler Installation Wiring ConnectionsFilling and Purging for Heating Boiler Installation OperationInlet GAS Pressure AdjustmentsPurging of GAS Line Manifold PressureFor Your Safety Read Before Operating For Your Safety Read Before Operating Description of MULTI-STAGE Firing System DIA-SCAN II Display Board Operating ProceduresControl System Green Status Lights Options/Features Setting ProceduresRed Fault Lights Outlet Probe Temperature ProbesYellow Parameter Set Lights Inlet ProbeApplication Hydronic Heating Procedure for Setting Tank Probe TemperatureProcedure for Setting Stage Differential Stage OneDisplay Stage Cycle Count Procedure for Setting Pump DelayLast Error Mode Appliance Operating SequencePreventative Maintenance Main BurnersDeliming LED Replacement PartsTroubleshooting Ignition System Insufficient AIR AIR Pressure Switch Stage No GAS Valve Power SensedCirculate Fault Flow Switch Power VentNEW Boiler Limited Warranty Replacement Parts