Hearth and Home Technologies Cinch Pipe & Termination Cap System Disassemble Vent Sections

Page 8

Secure the Vent Sections

Vertical sections of pipe must be supported every 8 ft after the 25 ft maximum unsupported rise. The vent support or plumber’s strap (spaced 120° apart) may be used to do this (see Figures 2.12 and 2.13).

Horizontal sections of vent must be supported every 5 ft with a vent support or plumber’s strap.

D. Disassemble Vent Sections

To disassemble any two pieces of pipe, rotate either section (see Figure 2.14), so that the seams on both pipe sections are aligned (see Figure 2.15). They can then be carefully pulled apart.

Figure 2.12 Securing Vertical Pipe Sections

WARNING

Fire Risk

Explosion Risk

Asphyxiation Risk

Use vent run supports per installation instructions.

Connect vent sections per installation instructions

Maintain all clearances to combustibles.

Do NOT allow vent to sag below connection point to appliance.

Maintain specifi ed slope (if required).

Improper support may allow vent to sag or separate.

Figure 2.13 Securing Horizontal Pipe Sections

Figure 2.14 Rotate Seams for Disassembly

Figure 2.15 Align and Disassembly Vent Sections

8Hearth & Home Technologies Inc. • Cinch Pipe & Term Caps • 4033-900 Rev K • 05/05

Image 8 Contents
Installation Instructions Any such action may cause a fire hazardParts and Descriptions Not shownCool ADD Trap CAP Specification Chart Clearances for the Vent Sections Penetrating a WallTop Vented Direct Vent Appliances Rear Vented Direct Vent AppliancesAttaching Vent to the Firebox Assembly Assemble Vent SectionsAssemble Pipe Sections Fire Risk Exhaust Fumes RiskAssemble Minimum Installation MI Sections Assemble Slip SectionsFire Risk Explosion Risk Asphyxiation Risk Disassemble Vent SectionsSecure the Vent Sections Install the Heat Shield and Horizontal Termination Cap Install the Horizontal Termination CapBurn Risk Heat Shield Requirements for Horizontal TerminationInstall the Firestop Spacer Install Attic Insulation ShieldVertical Penetration Framing Fire RiskInstall Roof Flashing and Vertical Termination Cap 20 Secure with Screws Roof Pitch Min. FtAssemble and Install Storm Collar Caulk around the top of the storm collar