For Vertical Terminations - To locate the vent and install the vent sections:

Locate and mark the vent centerpoint on the underside of the roof, and drive a nail through the centerpoint.

Make the outline of the roof hole around the centerpoint nail.

The size of the roof hole framing dimensions depend on the pitch of the roof. There MUST BE a 1-inch (25.4mm) clear- ance from the vertical vent pipe to combustible materials.

Mark the roof hole accordingly.

Cover the opening of the installed vent pipes.

Cut and frame the roof hole.

Use framing lumber the same size as the roof rafters and install the frame securely. Flashing anchored to the frame must withstand heavy winds.

Continue to install concentric vent sections up through the roof hole (for inside vent installations) or up past the roof line until you reach the appropriate distance above the roof (for outside terminations).

!WARNING: MAJOR U.S. BUILDING CODES SPECIFY MINIMUM CHIMNEY AND/OR

VENT HEIGHT ABOVE THE ROOF TOP. THESE MIN- IMUM HEIGHTS ARE NECESSARY IN THE INTER- EST OF SAFETY. SEE THE FOLLOWING DIAGRAM FOR MINIMUM HEIGHTS, PROVIDED THE TERMI- NATION CAP IS AT LEAST 20 INCHES FROM A VER- TICAL WALL AND 2-FEET BELOW A HORIZONTAL OVERHANG.

NOTE: This also pertains to vertical vent systems in- stalled on the outside of the building.

To seal the roof hole, and to divert rain and snow from the vent system:

Attach a flashing to the roof using nails, and use a non- hardening mastic around the edges of the flashing base where it meets the roof.

Attach a storm collar over the flashing joint to form a water-tight seal. Place non-hardening mastic around the joint, between the storm collar and the vertical pipe.

Slide the termination cap over the end of the vent pipe and snap into place.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCH MIN.

VERTICAL

MIN.

 

 

WALL

 

 

 

LOWEST

 

 

DISCHARGE

 

TERMINATION

OPENING

 

 

 

CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

H (min.) ft.

flat to 6/12

1.0

6/12 to 7/12

1.25

over 7/12 to 8/12

1.5

over 8/12 to 9/12

2.0

over 9/12 to 10/12

2.5

over 10/12 to 11/12

3.25

over 11/12 to 12/12

4.0

over 12/12 to 14/12

5.0

over 14/12 to 16/12

6.0

over 16/12 to 18/12

7.0

over 18/12 to 20/12

7.5

over 20/12 to 21/12

8.0

Figure 30. Minimum Height from Roof to Lowest Discharge Opening

32

Image 32
Contents ST-HVB-IPI LCOR-HVB-IPI RCOR-HVB-IPI What to do if you smell gasSafety and Warning Information Table of Contents Pier-HVB-IPI NG, LP Exploded Parts Diagram / Vue éclatée des pièces PIER-HVB-IPIST-HVB-IPI ST-HVB-IPI LCOR-HVB-IPI LCOR-HVB-IPI RCOR-HVB-IPI RCOR-HVB-IPI PIER-HVB-IPI, ST-HVB-IPI L&RCOR-HVB-IPI Installation Codes High Altitude InstallationsAppliance Certification CertificationANY Such Action MAY Possibly Cause a Fire Hazard Pre-install PreparationIntroducing the Heat & Glo Gas Fireplaces Diagram of the PIER-HVB-IPI Diagram of the ST-HVB-IPI Diagram of the LCOR-HVB-IPI and RCOR-HVB-IPI 121mmFireplace Dimensions and Locations Locating the FireplaceFraming the Fireplace Clearance RequirementsModel AT Each Joint Installing the Vent System Vent System ApprovalsTems or Components MAY be Used Identifying Vent ComponentsStraight UP Vertical Venting MAX .2 MStraight OUT Max. Run 24 610 mmVenting with One 90 Elbow Venting with Two 90 Elbows Venting with Two 90 Elbows Venting with three 90 elbows Venting with three 90 elbows Installing Vent Components Attach the First Vent Component to the Starting Collars Install Support Brackets Continue Adding Vent ComponentsAttic Firestop Positioned SO That the Arrow is Pointing UPVent Termination Minimum Clearances Minimum Height from Roof to Lowest Discharge Opening Positioning, Leveling, and Securing the Fireplace Gas Control SystemSecuring of a Fireplace Fireplace Junction BOX in a IPI SystemGas Supply Line Gas Pressure RequirementsAppliance Requirements Wiring the Fireplace For Intermittent Pilot Ignition WiringOperation using Battery Power Fan Wiring Diagram Optional Accessories Wall Switch Corner fan locationHearth Extensions FinishingANY Manner Installing Trim, Logs & Ember Material Using a 5/16 nut driver remove the two bolts see Figure Placing the Ember MaterialAfter the Installation Double-check for faulty componentsBefore Lighting the Fireplace Lighting the FireplaceFireplace Maintenance Important Turn OFF the GAS Before Servicing Your Fireplace