4100-I ACT WOOD INSERT

brick replacement instructions

The firebox is lined with high quality firebrick which has excep- tional insulating properties. There is no need for a grate, simply build a fire on the firebox of your insert.

1. Be certain coals are completely cold. Remove all old brick and ash from unit and vacuum out firebox.

6

4

1

1

4

6

2.Remove new brick set from box and lay out to THE diagram as shown.

3.Lay bottom bricks in unit.

4.Install rear bricks on the top of the bottom bricks. Slide top of bricks under clip on back of firebox wall and push bottom of brick back.

5.Install side bricks. Slide top of brick under clips on side of firebox and push the bottom of the brick until it is flush with the side of the unit.

Item

Brick Size

Qty in Set

1

9 x 4-1/2 x 1-1/4” with hole

2

2

9 x 4 x 1-1/4” with cut

2

3

4-1/2 x 3 x 1-1/4”

1

4

9 x 4-1/2 x 1-1/4”

12

5

9 x 3 x 1-1/4”

3

6

9 x 1-1/2 x 1-1/4”

2

5

 

 

 

4

 

 

 

4

4

5

4

4

 

 

 

4

 



4

2

 

 

2

Use Part #832-0550 when ordering indi- vidual brick and provide brick dimension or copy this page and mark the desired brick and take it to your authorized dealer.

5

4

4

4

2-1/4"

2

6-1/8"

BAFFLE REMOVAL & INSTALLATION

NOTE: The baffle material is 2700° Fiber Board. Removing hardware exposed to combustion processes can be frustrating. If your reason for removing the baffle is simply to clean the chimney, you have alternatives which will save time and effort. Call a qualified chimney sweep or an authorized Quadra-Fire dealer for details.

1.Remove all ash from firebox, and extinguish all hot embers before disposal into a metal container.

2.Remove ceramic blanket from above the baffle.

3.With a 3/16” Allen wrench, remove 2 front manifold tube retainer bolts on the air channel under the end of the front tubes. NOTE: Soak the bolts with penetrating oil for at least 15 minutes before trying to remove them. Figure 21A.

4.To remove manifold tubes, slide the tube to one side until one end is out of its hole. Then, while lifting that end of the fiber board baffle, pull tube up over the air channel and out of hole at the other end. It is necessary to remove the first two tubes in order to remove the baffle. NOTE: When replacing the manifold tubes, be sure the tube with the larger holes is placed in the front for your insert to operate properly.

5.Slide fiber board baffle forward to front of stove and straight out through door. Figure 21B.

6.To install the fiber board baffle, repeat steps 2 through 4 in reverse. Be sure the fiber board baffle and ceramic blanket are pushed back fully into position and the ceramic blanket lays flat.

First tube has larger holes

Allen wrench on retainer bolt

Figure 21A - Manifold tubes retaining bolt.

Ceramic Blanket

Baffle

Figure 21B - Baffle & Ceramic Blanket on top.

September 1, 2008

250-7201E

Page 21

Image 21
Contents Hot glass will cause burns Advanced Combustion Technology ACT007 Serial NumberModel Name Location Back side of left side panelTable of Contents Side View TOP ViewFront View Panel SizeSee Alternative Floor Protection Worksheet on SideWallRule A. These are safety requirements and are Installation recommendationsListings Chimney HEIGHT/DRAFTThermal Resistance R value Thermal Conductivity k valueConverting k to R Converting R to kOvalizing Round Stainless Steel Liners Chimney RequirementsFirestopping InsulationUSA only Installing Outside AirInstallation Into Masonry Fireplace Installation OptionsFactory-built zero clearance fireplace Installation Into a Factory Built Zero Clearance FireplaceAdjusting the Leveling Bolts Installation in CanadaLeveling Bolts and sheet metal shims Sheet Metal GuidesRe-install plate Outside AIR InstallationSecuring Liner to Chimney Ring Zero Clearance Fireplace Outside AIR Must be Turned to onPanel and Cast Trim must be ordered separately Panel SET and Cast Trim SETPanel and Gold Trim SET Completed ViewBlower Cord Location & Blower Control BOX with Switch Zero Clearance Adjustable Trim Support Door Handle AssemblyDoor Latch Adjustment Operation Burn Rates Operating TipsOpacity BTU / Hr Start-Up Air Control Primary ControlBurning Process Replace with 5mm ceramic glass only MaintenanceBaffle Removal & Installation Brick replacement instructionsExploded Views Ceramic BlanketDescription Service Parts and Accessories Part Description Alphabetical Order Date of Service Performed By Description of Service CONDITIONS, Exclusions & Limitation of Liability Hearth & Home Technologies Limited WarrantyHearth & Home Technologies Limited Warranty Cont’d Serial Number Date Purchased Date Installed Where PurchasedACT Wood Insert Telephone