INSTALLATION
DRAFT REQUIREMENTS
The appliance is merely one component of a larger sys- tem. The other equally important component is the vent- ing system which is necessary for achieving the required flow of combustion air to the fire chamber and for safely removing unwanted combustion byproducts from the ap- pliance. If the venting system's design does not promote these ends, the system may not function properly. Poorly functioning venting systems may create performance problems (i.e. smoking stove, poor heat output, fire goes out, window blackens, increased creosote buildup, etc.) as well as be a safety hazard. Some factors that may lead to performance problems are as follows:
•Oversized or undersized chimney.
•Excessive offsets in venting.
•Insufficient vertical height of chimney.
•Insufficient chimney termination height in relationship to roof.
•Insufficient ventilation.
•Lack of maintenance.
•Improper operation.
•Burning improper fuel (unit is approved for use with natural dry
•Down drafts in the chimney (may need a special wind cap).
To ensure that the venting system is functioning properly a draft test should be performed (see Draft Test Proce- dure on this page).
American National Standards Institute ANSI/NFPA 211-
92:A chimney or vent shall be so designed and con- structed to develop a flow sufficient to completely re- move all flue and vent gases to the outside atmosphere. The venting system shall satisfy the draft requirements of the connected appliance in accordance with the manu- facturer instructions.
DRAFT TEST PROCEDURE
After this appliance is installed a draft test should be per- formed to ensure proper draft. A qualified technician should perform the draft test procedure as follows:
1)Close all windows and doors in the dwelling.
2)Turn on or operate all appliances which remove air from the home (such as a furnace, heat pump, air conditioner, clothes dryer, exhaust fans, fireplaces, and other fuel burning appliances).
3)Drill a hole in the vent pipe per the draft gauge manufacturers instructions (to create a draft test port). Note: Hole location should be a minimum of 1 foot above flue outlet collar.
4)Start a fire (See How To Start And Maintain A Fire on page 16).
5)After the fire is well established
6)Install a screw to seal the draft test port in the vent pipe. If the draft test reading was not within the required range, correct the installation and repeat this procedure.
VENTILATION REQUIREMENTS / PROVIDE ADE- QUATE AIR FOR COMBUSTION
THE FRESH AIR REQUIREMENTS OF THIS APPLI- ANCE MUST BE MET WITHIN THE SPACE WHERE IT WILL BE INSTALLED. VENTILATION IS ESSENTIAL WHEN USING A SOLID FUEL BURNING HEATER.
In well insulated and weather tight homes, it may be diffi- cult to establish a good draft up the chimney (caused by a shortage of air in the home). The lack of air is caused by many common household appliances which exhaust air from the home (such as a furnace, heat pump, air conditioner, clothes dryer, exhaust fans, fireplaces, and other fuel burning appliances). Also, the combustion pro- cess of this heater uses oxygen from inside the dwelling. If the available fresh air delivery in the dwelling is insuffi- cient to support the demands of these appliances, prob- lems can result (i.e. excessive negative pressure can develop in the dwelling which will affect the rate at which this appliance can draft thus resulting in performance problems; See Draft Requirements on this page). To cor- rect this problem it may help to open a window (prefera- bly on the windward side of the house) or install a vent to provide
PAGE 11