State Industries SUF100199 Controls Pressure Switches ALL Models, Blocked Outlet Proving Switch

Page 28

ULTRAFORCE COMMERCIAL GAS WATER HEATER

SUF 120 thru 400 SERVICE HANDBOOK

CONTROLS – PRESSURE SWITCHES – ALL MODELS

All SUF models are provided with four pressure switches. T hese s witches ar e es sential to the safe an d pr oper op eration o f the uni t. T he switches are wired to the central control board (CCB) individually an d ea ch i s monitored individually. The (CCB) is set up to shut the unit down whenever there is a failure of any of the switches and declare a fault for each individual switch. It is important to understand the purpose of each switch.

Low Gas Pressure

Sw itch

Pressure

Sw itches

BLOCKED OUTLET PROVING SWITCH

The blocked outlet proving switch electrical contacts are normally closed. The blocked outlet proving switch el ectrical c ontacts w ill open on a rise in pressure. Check t o see i f t he c ondensate i s allowed to flow freely from the exhaust elbow and for obstructions in the exhaust venting and exhaust vent t erminal. Also c heck the t hat t he equivalent feet of vent pipe for the specific model has not been exceeded. Check the vent length tables on page 9

BLOCKED INLET PROVING SWITCH

The Blocked Inlet Proving switch electrical contacts are normally closed. The bl ocked i nlet pr oving switch el ectrical c ontacts w ill op en when an

increase in negative pressure (vacuum) occurs in the intake vent pipe. The switch is connected to the pressure tap on the PVC flange connected to the inlet of the blower. When this switch prevents the u nit f rom ig niting, most li kely the in take is blocked by some means. Verify that the air intake pipe and ai r i ntake v ent t erminal ar e f ree of obstructions that may prevent air from entering the unit. Also check the that the equivalent feet of vent pipe for the specific model has not been exceeded. Check the vent length tables on page 9

BLOWER PROVING SWITCH

The Blower Proving S witch i s pr ovided on t he heater t o v erify that t he f an i s op erating. It i s a positive pressure switch whose electrical contacts are normally open. Th e blower p roving switch electrical contacts will close on a rise in pressure as the blower increases the pressure in the burner. This switch i s c onnected t o t he b urner t ap b y a piece of Tygon (s oft pl astic) t ubing. This t ubing must be connected in order for the switch to close the electrical contacts. The controller requires that the electrical contacts on this p ressure switch b e open before it will allow the blower to come on. The control w ill declare a f ault on the U IM if ei ther condition occurs.

LOW GAS PRESSURE SWITCH

The Low Gas Pressure Switch electrical contacts are normally open. The low gas pressure switch electrical contacts will close on a rise pressure. The c ontacts w ill open w hen t he p ressure falls below the fixed set point. If this happens during a heating cycle a the burner will be shut down and a fault will be declared on the UIM.

State Water Heaters – Technical Training Department 27

Ashland City, Tennessee © 2009

Servicing should only be performed by a Qualified Service Agent

198152-002

Image 28
Contents Service Handbook Table of Contents Ultraforce Commercial GAS Water HeaterIntroduction QualificationsTools Required Digital MultimeterGAS Pressure Specifications General InformationAdjustment Procedure GAS Pressure SUF120 and 150 Models High Altitude Installations SUF 120High Altitude Installation GAS OrificeHigh Altitude Adjustment SUF 300,400 SUF 300,400Installation Tips SUF 300 Venting Tables SUF 120 Vent Length Table Equivalent Feet Meters 120 throughVenting Tables SUF 300,400 Vent Length Table Equivalent Feet Meters 300,400Venting ALL Models Single Pipe Power Vent Using Room AIR Venting ALL Models TWO Pipe Direct Vent Using Outside AIR Vent Termination Direct Vent ALL Models Direct Venting ALL Models Control Overview ALL Models Status Description IconAdjusting Tank Temperature Operating SET Point Differential DisplayChanging the Display Units Fault and Warning Conditions Advanced Diagnostic Information Access to the Current Fault or Warning Viewing Information About the Water Heater Control Sequence Typical ALL Models Control Sequence Flow Chart Controls Central Control Board CCB Remove these Screws to release CoverControls GAS Valve SUF SUF 120 thru 400 Service Handbook Controls GAS Valve SUF 199 Important Note High Altitude InstallationSupply gas pressure Controls GAS Valve , Orifice CHART- SUF300,400 Orifice Chart SUF 300,400Controls Pressure Switches ALL Models Blocked Outlet Proving SwitchTop View of Pressure Switches Controls Pressure Switches SUF 300,400 Blocked Inlet Pressure Switch Odel PressureUltraforce Commercial GAS Water Heater Control Timing HOT Surface Igniter / Flame Sensor / Control TimingFlame Sensor Blower Speed Control SUF 199 ModelBlower Motor Wires Black White RED Ground HOT NeutralAI1 LI1 LI2 LI3 LI4Variable Frequency Drive Blower Speed and Pressure Readings Voltage Frequency Speed Instructions VFD ModelSUF 400Wiring Diagram SUF 120 Wiring Diagram SUF Tennessee Waltz Parkway Ashland City, TN