IV. OPERATION
A.PRIOR TO OPERATION
1.Check all electrical connections to assure they are secure.
2.Check rigidity of unit mounting. Tighten all fasteners, if necessary.
3.Inspect piping, strainers, traps, fittings, etc.
B.INITIAL START-UP
1.Set thermostat to lowest position.
2.Turn on power supply to unit.
3.Open return gate valve, and then open supply gate valve to unit.
4.Raise thermostat setting to desired position.
5.Adjust louvers (if provided) for desired heat distribution.
6.To insure proper sequence of operation, cycle unit on and off a few times by raising and lowering thermostat setting.
7.Check for proper rotation of fan. All fans must rotate in a counterclockwise direction when viewed from the back (BH) of the unit heater.
8