GE GP94DNSRSA, GN94DNSRSA, GN75DNSRSA warranty Planning for Plumbing, Shown with optional pipe cover

Page 9

Installation Instructions

PLANNING FOR PLUMBING

(shown with optional pipe cover)

Unit

 

612

 

 

 

 

7″

12″

 

 

 

12″

18″ min.

 

412

 

 

Water

 

 

 

978 through

 

 

 

the wall

 

 

 

Gas

338

 

 

 

 

212

9″

 

 

 

 

 

 

212

212

212

 

 

Floor

6″

 

12″

 

 

Optional Pipe Cover (AGTPCM) shown shaded. Pipe cover not required, However, consideration should be taken in

the design of the rough plumbing to allow installation of unit and pipe cover.

Suggested area for Water and Gas lines to come through the wall so the optional pipe cover can be installed, if desired.

Water and Gas from below

The center of the pipes can be placed anywhere within the shaded area. The center of the pipes is recommended to be protruding only within 6″ of the mounting wall. Other specific installations may be different.

Be sure that the minimum elevation of the bottom of the unit is 16″ to meet the 36″ recommended clearance for the exhaust.

CAUTION: BURN HAZARD. Hot exhaust and vent may cause serious burns. Keep back from water heater unit. Keep small children and animals away from unit.

CAUTION: Hot Water outlet pipes leaving unit can be hot to touch. Insulation must be used for hot water pipes below 36″ due to burn risk to children.

NOTE: It is recommended to install the bottom

of the unit at least 18″ off the ground to minimize blockage and maintenance from debris and provide room for the optional Pipe Cover Accessory Model Number AGTPCM.

NOTE: Do not install electrical outlet directly below unit. Electrical outlet must be installed less than 6 feet from unit.

9

Image 9
Contents Safety Precautions Before BeginninginstallationFor Your Safety Models GN75DNSRSA, GN94DNSRSA, GP94DNSRSASafety Precautions Installation InstructionsTools YOU will Need Parts ProvidedDimensions GN75/GN94/GP94DNSRSADescription INTAKE/EXHAUST Guidelines Planning for VentingFlue Terminal Clearances Ansi Z21.10.3 CSA Flue Terminal ClearancesAdditional Clearances Vent Terminal Flue Installation Condensate Drain Horizontal Termination withCondensate Drain Shown with optional pipe cover Planning for PlumbingClearances for Water Heater Corrosive AtmospheresMounting the Water Heater Mounting the Waterheater Mounting the Water HeaterGAS Piping GAS PipingConnecting the Water Heater to the GAS Supply Water Piping Water PipingPressure Relief Valve Internal BUILT-IN Freezer ProtectionSupplemental Freeze Protection Connecting the Water Heater to the Water SupplyKEY Recommended Piping for Basic InstallationFreeze Protection For External Piping Electrical Requirements Electrical Connection InformationVenting Instructions Venting InstructionsCondensate Maximum Vent LengthFlue Installation Concentric Venting Vent ProductsProduct Parts Guidelines High Altitude InstallationsConfigurations Remote Controller InstallationLocation Mounting the ControllerCleaning the Inlet Filter Cleaning the Inlet FilterInstallation Checklist Technical Data Pressure Drop CurveOutlet Flow Data Ladder Diagram Page