Emerson XDCF Attaching Upper Liebert Xdcf Module, Preparing the Upper Module for Attachment

Page 15

Installation

4.4Attaching Upper Liebert XDCF Module

The upper Liebert XDCF module attaches to the Egenera BladeFrame cabinet with a mounting angle and four bolts.

Before the Liebert XDCF is mounted, the mounting angle and a two-piece deflector panel must be attached to the bottom of the Liebert XDCF and insulation must be applied to the left side.

4.4.1Preparing the Upper Module for Attachment

1.Position the mounting angle over the two mounting holes. The holes are near the center of the bottom of the Liebert XDCF module (see Figure 7).

2.Use two captive panel fasteners to attach the mounting angle to the bottom of the Liebert XDCF module. Tighten the fasteners securely, using a screwdriver, either a blade-type or Phillips.

3.Position the bottom deflector over the two mounting holes along the front edge of the bottom of the upper Liebert XDCF module (see Figure 10). The flanges along the edge should be on the top side.

4.Use two captive panel fasteners to attach the bottom deflector to the bottom of the upper Liebert XDCF module. Tighten the fasteners securely with a screwdriver, either a Phillips or a blade- type.

5.Position the second piece of the bottom deflector along the front edge of the deflector piece attached in Steps 3 and 4, matching the mounting slots in the two pieces. The flanges along the edge should be on the top side.

6.Use two captive panel fasteners to connect the deflector pieces. Tighten the fasteners finger-tight, leaving them loose enough to slide for good contact with the Egenera BladeFrame cabinet.

Figure 10 Upper Liebert XDCF attachment

 

 

Pipe support brackets

 

7-5/16"

not shown for clarity

 

3-9/16"

 

(186mm)

 

3-9/16"

(90mm)

 

1-7/16"

 

(90mm)

(37mm)

TOP VIEW

1-7/16"

 

(37mm)

 

 

Right Side

 

 

View

Coil

Bottom

Deflector

Bracket

Mounting

Angle

Gasket not shown for clarity

Captive panel fasteners

11

Image 15
Contents Liebert Xdcf Fluorinated Greenhouse Gas Requirements-European Union Important Safety GuidelinesTable of Contents Figures Liebert Xdcf component locations Example XD-CF10-BP-0 XD CFGeneral Product Information ReferencesParts Included With Liebert Xdcf Room PreparationProduct/System Description Equipment InspectionUnit Handling Recyclable Packaging Unpacking the Liebert Xdcf134a Mechanical ConsiderationsInstallation Installation ConsiderationsPreparing the Lower Module for Attachment Mounting Lower Liebert Xdcf ModuleLocator hole for lower unit stud Attaching Lower Liebert Xdcf ModuleLiebert XD Flex Pipe support panel attachment Attaching Liebert XD Flex Pipe Support PanelPreparing the Upper Module for Attachment Attaching Upper Liebert Xdcf ModuleAttaching Liebert XD Flex Pipe retainers Attaching Upper Liebert Xdcf ModuleHeader System Piping Connections and Piping Access PointsEuropean Union Fluorinated Greenhouse Gas Requirements Connection Methods and PointsConnecting Liebert XD Flex Pipes to Liebert Xdcf Modules Recommended Piping SizeTools Required Liebert XD prefabricated piping assembly Tools Required Return Supply Line InsulationChecklist for Proper Installation Fluorinated Greenhouse Gas Requirements MaintenanceLiebert Xdcf specifications SpecificationsSpecifications Specifications Page Ne t