5With the combi in the Hot Air mode with time on the timer, the door closed and the start switch is depressed

b The front display will include a lighted bar under the Hot Air symbol

When the heat circuit is energized the heat symbol will be energized

The cooking mode symbol will be energized.

The time display will invert and begin to count down.

cThe fan circuit is energized by the Control Board (A10) transmitting and receiving a signal from terminals 5,6,7 and 8 on connector X10 to terminals 3,4,5 and 6 of connector X28 on the Gas Board (A20)

dThe Gas board (A20) Transmits a signal from terminal 4 of connector X26 to the Motor Drive.

The motor Drive Board sends a signal through the thermal switch in the motor from Terminal 5 and receives on terminal 6

If the thermal switch is not open the Motor Drive Board (U10) sends 240 VAC 3 phase to the motor.

The motor reverses direction every 120 seconds with a 15 second coast.

NOTE: If the set temperature is less than 212 degrees F than fan will be pulsed on for 2 seconds every 60 seconds after the cabinet set temp (B6).

eHot air heat circuit is energized

A signal is sent from terminal 2 of connector X24 on the Gas Board (A20) to terminal 4 of connector X2 on the Hot Air Power Burner and Fan Control (U20) selecting the set speed of the combustion blower.

When this speed is attained the signal is sent from terminal 2 of connector X2 on the Hot Air Power Burner and Fan Control (U20) to terminal 3 of connector X24 on the Gas Board (A20)

A request for heat is sent from terminal 3 of connector X20 on the Gas Board (A20) to terminal 10 on connector X1 on the Hot Air Control Module (N20)

24 VAC is sent from terminal 2 of connector X2 on the Hot Air Control Module (N20) to the hot surface igniter (R20).

The gas valve is energized allowing gas and air into the burner chamber to be ignited by the hot surface igniter.

The Hot Air Burner Control Module (N20) senses at least 1.5 micro amps DC from the flame sensor (P1) at terminal 3 of connector X2 and sends a signal from terminal 2 of connector X1 to terminal 10 of connector X25 on the Gas Board (A20

69

Image 76
Contents Service & Parts Manual Table of Contents Service Parts Maintenance For the Installer Cleveland Statement of Policies General Information about Combis Installation Instructions Installation of the Combi General Instructions Page Cleveland Range, LLC Advanced Closed System offers the following advantages GAS Fired Boilerless TOP View Model χ OGB-6.20 Saves energy Model χ OGS-6.20 Optional Plate Rack holds 42 plates Control Panel Basic Operation Control Panel Detail View Function Indicators AT the END of the DAY or Shift Avoid scratching the oven chamber or engaging frame Page Semi-Automatic Cleaning of the Oven Chamber Page CONVOClean Automatic Cleaning System optional Page Descale Steam Generator General Safety for Descaling Page GAS Generator W Cleaning Light Gasket C6015020 Condensate Box o-ring C6015000QTY Part N0 Description GAS INJ W Cleaning ASSY, Control PANEL, SPRITZER, with Picto GAS GEN W Cleaning ASSEMBLY/WELDMENT, Intermediate TOP, 6.20/10.20 Spray Handle Shut Off Valve C6014003 ASSEMBLY, Intake PLATE, Gas Component Panel ASSEMBLY, GAS OGB 6.20 & 10.10 ModelsPanel ASSEMBLY, Models GASOGS 6.20 & 10.10 Models ASSEMBLY, Control PANEL, with Picto ALL ModelsBASE, GAS Injector With Cleaning OGS 10.10 Models BASE, GAS Injector No Cleaning OGS 10.10 Models BASE, GAS Generator With Cleaning OGB 6.20 Models BASE, GAS GENERATOR, no Cleaning OGB 6.20 Models BASE, GAS Injector With Cleaning OGS 6.20 ModelsPage ASSEMBLY, Water Hose SYSTEM, Condenser ASSEMBLY, Water Valve ALL GAS 10.10 ModelsModels ASSEMBLY, Water VALVE, INJECTOR, GAS ASSEMBLY, Water SUPPLY, Generator W/CLEANING System OEB & OGB 6.20 ModelsALL GAS 6.20 Models Push Button SWITCH, INJ, CHANGE-OVER Contact ASSEMBLY, Steam GENERATOR, GAS OGB 6.20 ModelsPUMP, Steam GENERATOR, GAS ALL GAS ModelsASSEMBLY, Burner INSERT, Steam GENERATOR, NAT GAS Venturi 40 KWBurner INSERT, HL, PRE-MOUNTED ASSEMBLY, Burner INSERT, AIR, LP & NAT GAS Burner INSERT, HL, PRE-MOUNTED, 6.10/6.20Door 6.20 Complete OES 6.20 & 10.10 ModelsSliding PLATE, Complete ALL 6.20 &10.10 ModelsALL 6.20 & 10.10 Models Exterior Sheeting STAND, ASSEMBLY, Closed Base 10 & 10.10 ModelsPage Page Page Page ASSEMBLY, Stacking KIT, GAS Models 20 on 6.20 or 10 on 6.10 orASSEMBLY, Stacking KIT, Electric Models PIPE, Steam EXHAUST, ELECTRIC, Stacking KITCleveland Range OGB 6.20/10.10 Sequence of Operations Page Page Page Page Page Page Page Cleveland RANGE, LLC Wiring Diagram X12GND X23 X10 N20 N21 IVE Ladderdiagram Ladder DI RAM Cleveland Range OGS 6.20/10.10 Sequence of Operations Page Page Page Page Page OGS 6.20/10.10 Preliminary X39 A12 Preliminary Ladder Diagram Ladder