INSTALLATION START-UP REQUEST CHECKLIST
Machine Model Number: 17/19EX | Serial Number: |
|
| ||||||
To: |
|
|
| Date |
|
| |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
| Project Name |
|
| |
Attn: |
|
|
|
|
|
|
| ||
|
|
|
|
|
| Carrier Job Number |
|
|
The following information provides the status of the chiller installation.
YES/NO
(N/A)
1.The machine is level.
2.The machine components are installed and connected in accordance with the installation instructions.
3.The isolation package and grouting (if necessary) are installed.
4.The relief valves are piped to the atmosphere.
5.All piping is installed and supported. Direction of ¯ow
is indicated in accordance with the installation instructions and job prints.
a.Chilled water piping
b.Condenser water piping
c.Waterbox drain piping
d.Pumpout unit condenser piping (if installed)
e.Oil cooler water piping (FA compressors only)
f.Other
6.Gages are installed as called for on the job prints required to establish design ¯ow for the cooler and condenser.
a.Water pressure gages IN and OUT
b.Water temperature gages IN and OUT
7.The machine's starter wiring is complete. The wiring is installed per installation instructions and certi®ed prints.
a.Power wiring to compressor motor. (Motor leads will not be taped until the Carrier technician megger tests the motor.)
b.Oil pump wiring
c.Oil heater/control wiring
d.Other
DATE TO BE COMPLETED
8.The motor starter has not been supplied by Carrier. It has been installed according to the manufacturer's instructions.
9.The motor starter has not been supplied by Carrier and it has been checked for proper operation.
COMMENTS: