Carrier 19EX, 17 installation instructions Testing YES/NO Date to be Completed

Page 32

TESTING

YES/NO

DATE TO BE

COMPLETED

 

 

1.The cooling tower fan has been checked for blade pitch and proper operation.

2.The chilled water and condenser water lines have been:

a.Filled

b.Tested

c.Flushed

d.Vented

e.Strainers cleaned

3.The chilled water and condenser water pumps have been checked for proper rotation and ¯ow.

4.The following cooling load will be available for start-up:

a.25%

b.50%

c.75%

d.100%

5.The refrigerant charge is at the machine.

6.Services such as electrical power and control air will be avail- able at start-up.

7.The electrical and mechanical representatives will be available to assist in commissioning the machine.

8.The customer's operators will be available to receive instruc- tions for proper operation of the chiller after start-up.

Concerns about the installation/request for additional assistance:

I am aware that the start-up time for a Carrier chiller can take between 2 and 6 days depending on the model of the machine and the options and accessories used with it.

Your contact at the job site will be

Phone number

Beeper number

Fax number

In accordance with our contract, we hereby request the services of your technician to render start-up services per contract terms

for this job on(Date). I understand that the technician's time will be charged as extra services due to correcting items in this checklist that are incomplete.

Signature of Purchaser

Signature of Job Site Supervisor

Copyright 1996 Carrier Corporation

Manufacturer reserves the right to discontinue, or change at any time, speci®cations or designs without notice and without incurring obligations.

Book

2

2

 

PC 211

Catalog No. 531-749

Printed in U.S.A.

Form 17/19EX-2SI

Pg CL-2

3-96

Replaces: 17/19EX-1SI

Tab

5a

5d

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - CUT ALONG DOTTED LINE

Image 32
Contents Installation Instructions Contents Model Number Identication Typical 19EX Installation 19EXTypical 17EX Installation 17EX Front View 19EX Front ViewTypical Top View 19EX Shown Item no Torque Ft-lbCondenser LENGTH² Width Height Tube Pull Component DIAMETER²² LENGTH²² Diameter LengthHeat Nozzle TypeCondenser Total Weight Condenser Charge Refrigerant ChargeDry Operating²² Refrigerant Water Dry Operating²² RefrigerantAdditional Cooler Weights Additional Condenser WeightsAuxiliary Connection Sizes CondenserTotal 19EX Motor Weights 60 Hz Total 19EX Motor Weights 50 HzCompressor Weights Total 17EX Drive Component WeightsÐ 17EX Motors Ð Total Weight, Lbs English Ð 17EX Motors Ð Total Weight, Kg SIPsi KPa Marine Waterbox Cover WeightsNIH Waterbox Cover Weights Dimensions Cooler Sizes 31-33Cooler Sizes Ft-in 31-33Machine Vibration Isolation Connect Piping NOZZLE-IN-HEAD Waterboxes Frame 3 and 5 Marine WaterboxesCooler Waterbox Pass Out ArrFrame 4 Marine Waterboxes Pumpout UnitWater Piping, Oil Cooler to Chilled Water Circuit Typical Relief Valve Locations and Data ValvesIndividual Component Ratings PH-HZGeneral Page General Oil Pump Wiring 19EX Shown8772 02525Insulation Requirements 11¤8 Foam Tubing 15¤819EX Chillers Front View Plan ViewInstallation START-UP Request Checklist Testing YES/NO Date to be Completed