TESTING | YES/NO | DATE TO BE | |
COMPLETED | |||
|
|
1.The cooling tower fan has been checked for blade pitch and proper operation.
2.The chilled water and condenser water lines have been:
a.Filled
b.Tested
c.Flushed
d.Vented
e.Strainers cleaned
3.The chilled water and condenser water pumps have been checked for proper rotation and ¯ow.
4.The following cooling load will be available for
a.25%
b.50%
c.75%
d.100%
5.The refrigerant charge is at the machine.
6.Services such as electrical power and control air will be avail- able at
7.The electrical and mechanical representatives will be available to assist in commissioning the machine.
8.The customer's operators will be available to receive instruc- tions for proper operation of the chiller after
Concerns about the installation/request for additional assistance:
I am aware that the
Your contact at the job site will be
Phone number
Beeper number
Fax number
In accordance with our contract, we hereby request the services of your technician to render
for this job on(Date). I understand that the technician's time will be charged as extra services due to correcting items in this checklist that are incomplete.
Signature of Purchaser
Signature of Job Site Supervisor
Copyright 1996 Carrier Corporation
Manufacturer reserves the right to discontinue, or change at any time, speci®cations or designs without notice and without incurring obligations.