Moyer Diebel MH-60M3, MH-6NM3, MH-6LM3 technical manual Installation, 20-22 PSI/138-151.8 kPa

Page 14

INSTALLATION

INSTALLATION (Cont.)

 

Plumbing Connections

 

NOTE:

 

Plumbing connections must comply with

 

all applicable sanitary and plumbing

 

codes.

 

Water Connections

12"

 

1. All MH series dishwashers require a single,

[305mm]

 

hot water supply.

 

 

FLOOR

The hot water connection to all MH

 

series dishwashers is 3/4" NPT.

 

The connection is made from

 

underneath the dishwasher.

 

 

Figure 7

 

Hot Water Connection

The following minimum water

(MH-60 Only)

3/4" NPT

temperatures are recommended:

 

MH-60 with built-in 40° rise electric booster (Minimum 140°F/60°C) (Min./Max. flow pressure

20-22 PSI/138-151.8 kPa)

MH-60 with built-in 70° rise electric booster (Minimum 110°F/43°C) (Min./Max. flow pressure

20-22 PSI/138-151.8 kPa)

MH-6N without built-in booster (Minimum 180°F/70°C) (Min./Max. flow pressure 20-22 PSI/138-151.8 kPa)

MH-6L low temperature (Minimum 120°F/49°C- 140°F/60°C Optimum)

(Min./Max. flow pressure 20-22 PSI/138-151.8 kPa)

Refer to Figs. 7 and 8

12"

[305mm]

FLOOR

Figure 8

Hot Water Connection

(MH-6N, MH-6L Only)

3/4" NPT

12

Image 14
Contents MH-6NM3 MH-6LM3Moyer Diebel, US Moyer Diebel, Limited Revision History CommentsContents List of Figures Limited Warranty Introduction Welcome to Moyer DiebelOptions MH-60 only AccessoriesStandard Equipment includes Model Installation Unpack the dishwasherPlacement for Corner Operation Installation Electrical ConnectionsHinged Control Panel Installation 20-22 PSI/138-151.8 kPaVentilation Water ConnectionsDrain Connections Chemical Dispenser Signal Terminal Block Chemical ConnectionsMH-6L Only MH-60, 6NMH-60, 6N, 6L Models MH-60 and MH-6N do not require sanitizerComplete the installation Initial START-UPCheck Wash Water Temperature Initial START-UPPower Check Final Rinse Water Temperature Check Final Rinse Water PressureDrain the dishwasher Extended Wash OperationComplete the initial start-up Initial START-UP Operation Summary Action ResultEvery 8 Hours or at the End of the Day CleaningEvery 2 Hours or After Each Meal Period Deliming Troubleshooting Condition Cause SolutionTroubleshooting Schematics Basic ServiceTroubleshooting ToolsElectrical Service Motor OverloadsElectrical Service Timers Cycle TimerConfiguration a Electrical Service Motor Connections LineMechanical Service Pump Seal ReplacementReplacement Parts MH-60/6N/6L Doors and Panels Doors and Panels Part Item No Part DescriptionMH-60/6N/6L Door Guides, Stops, and Lift Bracket Door GUIDES, STOPS, and Lift Bracket Part Item No Part Description QtyMH-60/6N/6L Door Handle, Spring Assembly, and Safety Switch Door HANDLE, Spring ASSEMBLY, and Safety Switch BUSHING, Side DoorMH-60/6N/6L Track Assembly Corner configuration shown Track Assembly GUIDE, Left HandFront Side Left WASH/RINSE Spray Piping MH-60/6N/6L Wash/Rinse Spray Arms WASH/RINSE Spray Arms MH-60/6N/6L Drain Assembly and Scrap Screens Drain Assembly and Scrap Screens RETAINER, OverflowMH-60/6N/6L Wash Tank Heat and Thermostats Wash Tank Heat and Thermostats WASHER, Lock 1/4 Split SSTValve Fill From Piping MH-60 only Electric Booster and Thermostats WASHER, Lock 1/4 SplitTo Upper MH-60 only Lower Fill Piping Assembly Replacement Parts Water in from Lower Piping MH-60/6N only Upper Fill Piping Assembly Customer Water MH-6N/6L only Lower Fill Piping Assembly MH-6L Only Upper Fill Piping Assembly MH-6L only Upper Fill Piping Assembly MH-60/6N/6L Pump Assembly Pump Assembly Backing PLATE, MachinedMH-60/6N/6L Control Panel and Gauges Control Panel and Gauges MH-60/6N/6L Control Cabinet Control Cabinet Dishracks and PRV Dishracks and PRV Part Part Description Item NoThis Intentionally Left Blank Electrical Schematic / 3 Phase MH-60, 6N, 6L Electrical Schematic / 1 Phase MH-60, 6N, 6L