Moyer Diebel MH-60M3, MH-6NM3, MH-6LM3 technical manual Initial START-UP

Page 23

INITIAL START-UP

INITIAL START-UP (Cont.)

13

Drain the dishwasher (Cont.)

Be sure the drain-overflow seal is secure on the drain-overflow assembly.

14

Remove the scrap screens and check the drain located in the bottom of the dishwasher wash tank.

Make sure that the building drain handles the water flow exiting the dishwasher.

Clean the interior of the wash tank of any foreign material.

Leave the doors open to air dry the interior of the dishwasher.

The initial start-up is complete.

21

Image 23
Contents MH-6LM3 MH-6NM3Moyer Diebel, US Moyer Diebel, Limited Comments Revision HistoryContents List of Figures Limited Warranty Welcome to Moyer Diebel IntroductionOptions MH-60 only AccessoriesStandard Equipment includes Model Unpack the dishwasher InstallationPlacement for Corner Operation Electrical Connections InstallationHinged Control Panel 20-22 PSI/138-151.8 kPa InstallationVentilation Water ConnectionsDrain Connections Chemical Connections Chemical Dispenser Signal Terminal BlockModels MH-60 and MH-6N do not require sanitizer MH-60, 6NMH-60, 6N, 6L MH-6L OnlyInitial START-UP Complete the installationInitial START-UP Check Wash Water TemperaturePower Check Final Rinse Water Pressure Check Final Rinse Water TemperatureDrain the dishwasher Extended Wash OperationComplete the initial start-up Initial START-UP Action Result Operation SummaryEvery 8 Hours or at the End of the Day CleaningEvery 2 Hours or After Each Meal Period Deliming Condition Cause Solution TroubleshootingTroubleshooting Tools Basic ServiceTroubleshooting SchematicsMotor Overloads Electrical ServiceCycle Timer Electrical Service TimersConfiguration a Line Electrical Service Motor ConnectionsPump Seal Replacement Mechanical ServiceReplacement Parts MH-60/6N/6L Doors and Panels Part Item No Part Description Doors and PanelsMH-60/6N/6L Door Guides, Stops, and Lift Bracket Part Item No Part Description Qty Door GUIDES, STOPS, and Lift BracketMH-60/6N/6L Door Handle, Spring Assembly, and Safety Switch BUSHING, Side Door Door HANDLE, Spring ASSEMBLY, and Safety SwitchMH-60/6N/6L Track Assembly Corner configuration shown GUIDE, Left Hand Track AssemblyFront Side Left WASH/RINSE Spray Piping MH-60/6N/6L Wash/Rinse Spray Arms WASH/RINSE Spray Arms MH-60/6N/6L Drain Assembly and Scrap Screens RETAINER, Overflow Drain Assembly and Scrap ScreensMH-60/6N/6L Wash Tank Heat and Thermostats WASHER, Lock 1/4 Split SST Wash Tank Heat and ThermostatsValve Fill From Piping WASHER, Lock 1/4 Split MH-60 only Electric Booster and ThermostatsTo Upper MH-60 only Lower Fill Piping Assembly Replacement Parts Water in from Lower Piping MH-60/6N only Upper Fill Piping Assembly Customer Water MH-6N/6L only Lower Fill Piping Assembly MH-6L Only Upper Fill Piping Assembly MH-6L only Upper Fill Piping Assembly MH-60/6N/6L Pump Assembly Backing PLATE, Machined Pump AssemblyMH-60/6N/6L Control Panel and Gauges Control Panel and Gauges MH-60/6N/6L Control Cabinet Control Cabinet Dishracks and PRV Part Part Description Item No Dishracks and PRVThis Intentionally Left Blank Electrical Schematic / 3 Phase MH-60, 6N, 6L Electrical Schematic / 1 Phase MH-60, 6N, 6L