TOWERS AND DOORS INSTALLATION
STEP 4
Place the center support rail into slot on each tower. If rail does not readily fit into slots, it may be necessary to loosen the bolts holding towers to base (it may only be necessary to loosen one tower). DO NOT FORCE CENTER RAIL INTO SLOTS. With center support rail in position, install hold down brackets but do not tighten screws. Do not mount side rail or short rail(s) at this time. See HOLD DOWN BRACKET detail. Side rail and short rail(s) must installed after all finish tiling, trim, and sealing are completed.
SCREW (8 PER WATER TOWER) (4 PER AIR TOWER)
RAIL HOLD DOWN BRACKET (1 PER AIR TOWER)
(2 PER WATER TOWER)
SIDE RAIL OR
SHORT RAIL
HOLD DOWN BRACKET DETAIL
SHORT RAIL (1 RAIL WITH 2 WALL) (2 RAILS WITH 3 WALL)
HOLD DOWN BRACKETS (5)
CENTER SUPPORT RAIL
WATER TOWER DOOR POST
RAIL BRACKET (2 WALL ONLY)
COVER CAP (2 WALL ONLY)
SIDE RAIL
(2 WALL ONLY)
WATER TOWER JAMB (2 WALL ONLY)
STEP 5
Add blocking if the side wall post does not rest on a wall stud. Level side wall post and anchor side wall post to wall stud or blocking using 3 screws provided. Do not screw tower jamb to side
wall post at this time.
| BLOCKING |
| SIDE WALL POST |
SIDE WALL POST | BLOCKING |
| SCREW |
| SCREW |
SCREW |
|
| WATER TOWER |
SCREW | SIDE JAMB |
| |
SIDE JAMB |
|
| 9 |