Allied Telesis GS900/5E manual Powering On the Switch

Models: GS900/5E

1 40
Download 40 pages 33.63 Kb
Page 36
Image 36
Powering On the Switch

Chapter 2: Installation

Powering On the Switch

To apply power to the AT-GS900/16 and AT-GS900/24 switches, perform the following procedure:

1.Apply AC power to the switch by plugging the power cord into the AC power connector on the back panel of the unit, as illustrated in Figure 13.

Warning

Power cord is used as a disconnection device: To de-energize equipment, disconnect the power cord.  E3

100-

VAC~

 

612

Figure 13. Connecting the AC Power Connector to Switch

2.Plug the other end or the power cord into a wall outlet.

3.Verify that the POWER LED is green. If the LED is OFF, refer to “Troubleshooting” on page 37.

The switch is ready for network operations.

36

Page 36
Image 36
Allied Telesis GS900/5E manual Powering On the Switch