Optional: Install the Open Racks

After you have installed the inner rails on the chassis, you are ready to install the outer rails of rail assemblies to the rack.

NOTE: The rails are designed to fit in the racks with the depth of 28” to 33”.

Determine the placement of each component in the rack before you install the rails.

Install the heaviest server components on the bottom of the rack first, and then work up.

1.In the package, locate a pair of front (short) and rear (long) brackets. Please note that the brackets are marked with Up/Front Arrows (front) and Up/Rear arrows (rear).

2.Secure the front (short) bracket (marked with the Up/Front arrows) to the outer rail with two Type G screws as shown below.