SCR DC Controls

(For 19H and 20H SCR DC Controls).

Single Expansion Board Installation

Procedure:

1.Be sure drive operation is terminated and secured.

2.Remove all power sources from the control.

3.Wait at least 5 minutes for internal capacitors to discharge.

4.Slide the expansion board male connector into the female connector of the control board. See Figure 3-4.

5.Securely mount the expansion board to the sheet metal mounting plate using the #6 screws provided in the installation hardware. See Figure 3-5.

6.The mechanical installation of the expansion board is now complete. Refer to the Group 1 manual and configure the jumpers as desired. Also complete the wiring before you proceed to step 7.

7.Restore all power sources to the control.

8.Restore drive operation.

3-10 Installation

Page 19
Image 19
Baldor Resolver to Digital Expansion Board, EXB009A01 manual For 19H and 20H SCR DC Controls