You must perform the following before operating the system:
•If generator is installed in an area regularly subjected to temperatures below 40°F (4°C), select a 50 second warm up time by moving jumper JP2 (C) installed on transfer switch control board from ‘20’ position to ‘50’ position.
•Set the DPSW1 (A) and DPSW2 (B) dipswitches on the transfer switch control board to match the kW rating of the standby generator, as described in Setting Dipswitches.
NOTICE Use extreme caution when setting dipswitches or damage to control board will result.
• Use a pencil or small piece of plastic to set the dipswitch.
• NEVER use a screwdriver or any type of metal object to set dipswitches.
The “On” position for the dipswitches is the switch number ON THE TRANSFER SWITCH CONTROL BOARD, not on the switch. For example, for an 18,000 watt generator, set DPSW2 dipswitch 10 to “On” position. Set DPSW1 dipswitch 8 to “On” position. 10,000 plus 8000 equals 18,000 watts. Set only one switch to “On” position on DPSW1 and DPSW2.
Refer to following chart for proper switch selection(s).
DPSW1 | A | kW Rating | DPSW | DPSW | |
| B | of | #1 “ON” | #2 “ON” | |
| Generator | Position | Position | ||
|
| ||||
|
| 7kW | 7 | 0 | |
|
| 8kW | 8 | 0 | |
|
| 9kW | 9 | 0 | |
|
| 10kW* | 0 | 10 | |
operation. If dipswitches are set when powerREPRODUCTION | 10 | ||||
|
| 11kW* | 1 | ||
|
| 12kW | 2 | 10 | |
DPSW2 | JP2 | 13kW* | 3 | 10 | |
|
| 14kW | 4 | 10 | |
|
| 15kW | 5 | 10 | |
|
| 16kW | 6 | 10 | |
|
| 17kW | 7 | 10 | |
Setting Dipswitches |
| 18kW | 8 | 10 | |
Dipswitches are used to adjust control board operation | 19kW | 9 | 10 | ||
| FOR |
|
|
| |
based on generator capacity. DPSW1 and DPSW2 switches | 20kW | 0 | 20 | ||
are set to correspond to total system kW rating. Dipswitch | 30kW | 0 | 30 | ||
DPSW1 (A) has units of 1,000NOTwatts; Dipswitch DPSW2 (B) | 45kW | 5 | 40 | ||
has units of |
| ||||
10,000 watts. |
| 48kW | 8 | 40 | |
Set dipswitches with utility and generator power removed | 50kW | 0 | 50 | ||
from the transfer switch to ensure proper control system | 60kW | 0 | 60 | ||
| is present at | * For generators with a rating that includes 500 Watts, round down to | |||
transfer switch, a power reset needs to be performed before |
| next lowest rating |
| ||
the new dipswitch settings will take effect. Power reset is |
| (example: 13.5 kW set to 13kW) |
| ||
when all power is removed from the transfer switch and then |
|
|
| ||
reintroduced after 30 seconds. |
| NOTICE Air density is less at high altitudes, resulting in | |||
NOTICE An FC_8 will occur on standby generator control | |||||
less available engine power. Specifically, engine power will | |||||
board if dipswitches are not properly established as noted | |||||
decrease 3.5% for each 1,000 feet (300 meters) above sea | |||||
above. |
| ||||
| level and 1% for each 10° F (5.6°C) above 77°F (25°C). | ||||
|
| ||||
|
| Generators located in these conditions must have the transfer | |||
|
| switch programmed appropriately for this power decrease. |
13