Testing the Symphony™ II Power

4. Verify signal was received by remote module set to

Management System

priority one. Follow the test guidelines for each module:

 

50 Amp Module: Relay contacts will be closed. Relay

WARNING Testing must only be performed by

and communication LED’s will be green. Appliance/load

qualified personnel. Equipment contains high

will have power.

voltage that could cause personal injury or death.

 

• Despite the safe design of the system, operating this equipment imprudently, neglecting its maintenance or being careless can cause possible injury or death.

The Symphony II system can be tested under either utility power or generator power. Only one priority LED and associated remote module will be powered (ON) at a time during test mode.

If TEST is not pressed again within 4 minutes AND

 

 

 

testing is being done under utility power, all managed

 

 

 

loads will resume operation under utility power after a

Closed

Open

 

five minute delay.

 

 

 

 

If TEST is not pressed again within 4 minutes AND

Low Voltage Module (Single or Dual): Verify

 

testing is being done under generator power, managed

 

continuity across low voltage control wiring contacts

 

loads will be added in the priority order set for

 

 

 

(A). Communication LED will be green. Appliance/load

 

each load.

 

 

 

 

 

 

 

 

 

will have power.

 

 

 

 

 

 

 

REPRODUCTION

The test procedure in generator mode is as follows:

 

 

1.

Turn the utility service disconnect circuit breaker

A

 

 

feeding the transfer switch contactor to the

 

 

2.

“OFF” position.

 

 

 

 

 

 

After transfer to generator power, verify communication

 

 

3.

LED is green on each remote module.

 

 

 

 

Press the TEST button (B) on the Symphony II system

 

 

 

control board. The Symphony II system control board

 

 

 

priority 1 LED (C) and load connected to remote

5. Press the TEST button on the Symphony II system

 

module set to priority 1 will turn

.

 

 

 

NOB T

 

 

control board. The priority 1 LED and load connected to

 

 

 

remote module set to priority 1 will turn OFF.

 

 

 

50 Amp Module: If off, relay LED status is off.

 

 

 

 

 

 

 

 

Communication LED status is green.

 

 

 

 

 

 

 

 

Low Voltage Module (Single or Dual): If off, low

 

 

 

 

 

 

 

 

voltage communication LED status is green. Continuity

 

 

 

 

 

 

 

 

will not be measured across low voltage contacts.

 

 

 

 

 

 

 

 

The priority 2 LED (

) and load connected to remote

 

 

 

 

 

 

 

 

module set to priority 2 will turn ON. Repeat step 4 for

 

 

 

 

 

 

 

 

each priority number being managed.

 

 

A

 

 

C

 

6. Each subsequent press of the TEST button cycles to

 

 

 

 

 

the next lower priority, through priority 8. After priority

 

 

 

 

 

 

 

 

8, press TEST button one time to exit test mode. The

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

D

system will reset and be ready to add loads

 

LEDLEDLEDLEDLEDLED

LEDLEDLED

 

in 5 minutes.

7. To return to utility power, turn the utility disconnect circuit breaker to the ON position. All managed loads will be turned off and turn back on after 5 minutes.