STEP #1

In-Ground Post Assembly

7.Arrange with your local gas company or licensed contractor to have a gas supply line connected to the inlet of the stainless steel flex tube assembly. The gas supply must have a shutoff valve that is close to the post in case of emergency and must

be shutoff when the grill is not in use. See Figure 8.

The grill and its individual shutoff valves must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 PSIG. The grill must be isolated from the gas supply piping system by closing its individual manual shutoff valves during any pres- sure testing of the gas supply piping system at test pressures equal to or less than 1/2 PSIG.

STEP #1

STEP #2

WARNING: DO NOT SUPPLY LP GAS TO A GRILL DE-

 

SIGNED FOR NATURAL GAS OR NATURAL GAS TO A

 

GRILL DESIGNED FOR LP GAS.

 

Gas leak tests should be completed as directed in the grill

Owner’s Manual.

Completely fill remaining hole with soil.

24 3/4”

ABOVE GRADE

Figure 8

8.Install the post access door and grease cup as shown in Fig- ures 9 and 10.

STEP #3 STEP #4

NOTE: GAS LINE REMOVED FOR CLARITY

Figure 10

9.Continue assembly as directed by the Owner’s Manual pack- aged with the grill head.

Test for gas leaks as directed by the grill’s Owners Manual. The grill and its individual shutoff valves must be disconnected from the gas supply piping system during any pressure testing of that system at test pressures in excess of 1/2 PSIG. The grill must be isolated from the gas supply piping system by closing its individual manual shutoff valves during any pressure testing of the gas supply piping system at test pressures equal to or less than 1/2 PSIG.

STEP #2 WARNING: DO NOT SUPPLY LP GAS TO A GRILL DE- SIGNED FOR NATURAL GAS OR NATURAL GAS TO A GRILL DESIGNED FOR LP GAS.

Gas leak tests should be completed as directed in the grill owner’s manual.