Burnham ES2 manual Unpack the Crate, Position the Boiler

Models: ES2

1 52
Download 52 pages 24.08 Kb
Page 7
Image 7

1. Unpack the Crate

THE BOILER IS TOP-HEAVY. Do not allow it to tip over.

1.Remove the sleeve.

2.Remove the contents from the skid, except the boiler.

3.Remove the four (4) hex-drive lag screws holding the boiler to the skid (Figure 1-a).

1-a

4.Tip the boiler and shimmy it off the skid.

1-b

2.Position the Boiler

WARNINGS

OBSERVE MINIMUM CLEARANCES to combustible walls and ceilings to avoid potential fire hazard.

DO NOT INSTALL ON CARPET. This may cause a fire.

INSTALLING THE BOILER NEAR A SOURCE OF FLAMMABLE LIQUIDS or gases may cause fire or explosion.

CLEAN BURNERS DAILY if operating the boiler in a dusty environment.

PROTECT IGNITION SYSTEM COMPONENTS from sources of water that may spray, drip, or rain on them during installation or service.

1.Slide the boiler into desired location.

2.Meet the minimum clearances to combustible construction per the Specification Section of this manual.

3.Allow 24" service clearance in front and on the left side of the boiler.

4.Level the boiler, using shims as necessary.



Page 7
Image 7
Burnham ES2 manual Unpack the Crate, Position the Boiler