Section 3. TLX106 Instrumentation Installation

3.1Enclosure, Datalogger, Power Supply

3.1.1 Battery Option Installation

Solar Panel or 16 VAC

Power Cable

S

FIGURE 3.1-1. Rechargeable Power Mounting and Connections

a)Sealed Rechargeable Battery Option: Install the kit as shown in Figure 3.1-1. An unregulated solar panel or 17 to 24 VAC must be used with the rechargeable battery at all times. In either case, power is routed through the Heyco fitting on the enclosure back and connected to the CHG ports by depressing connector levers. Polarity of the CHG connection does not matter. Install the rechargeable battery and plug the battery lead into the connector labeled “ LA” .

NOTE Press the connector levers gently or they might break.

3.1.2 Solar Panel Installation

FIGURE 3.1-2. Solar Panel Mounting

a)Mount the solar panel to the tower using the mounting brackets as shown in Figure 3.1-2. Mount the solar panel to the tower so it faces south (northern hemisphere). Position it as high off the ground as practical, ensuring it cannot interfere with air flow or sunlight around the sensors.

3-2