![a30-4871](/images/new-backgrounds/33835/3383525x1.webp)
UNITS WITH
Proper closed system design and installation procedures should be followed closely. The system must be constructed with pressure tight components and thoroughly tested for installation leaks.
Figure 11 shows a typical installation with components that might be installed with the hydronic package of the 30RAP unit. The
NOTE: For units with single pumps, it is recommended that isolation (shutoff) valves be placed exterior to the unit to allow removal and service of the entire pump assembly, if necessary. Units with dual pumps have pump isolation valves provided. Also, if the unit is isolated with valves, a properly sized pressure relief valve should be installed in
the piping between the unit and the valves, following all applicable state and local codes.
System Pressurization — A proper initial cold fill pressure must be established before the filling of the unit. The initial cold fill pressure is the pressure applied at the filling point to fill a system to its highest point, plus a minimum pressure at the top of the system (4 psi minimum) to operate air vents and pos- itively pressurize the system.
The compression tank (sometimes called expansion tank) is very important to system pressurization. The compression tank actually serves several purposes:
1.Provide net positive suction head required (NPSHR) for the pump to operate satisfactorily.
2.Set system pressure.
3.Accommodate expansion/contraction of water due to temperature changes.
4.Acts as a pressure reference for the pump.
The compression tank pressure must be set BEFORE the system is filled. The tanks are
Tank Pressure = 4 + (height from tank to top of system in feet/“X”)
[27.6 + (height in m x 22.6/”X”)]
2
14
12 11
1
13
7
5 6
3
4
6
12 | 11 | 9 |
|
|
|
|
|
| 8 | ||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
|
|
|
|
|
|
|
| LEGEND |
|
1 | — | 8 | — | Flow Switch | |
2 | — Expansion Tank | 9 | — | Balance Valve/Drain Plug |
|
3 | — Pump | 10 | — | Pressure Relief |
|
4 | — Electric Heater | 11 | — | Isolation Valves |
|
5 | — Air Vent Connection Port | 12 | — | Flex Connections |
|
6 | — Pressure/Temperature Access Port | 13 | — | Pressure Reducing/Fill Valve |
|
7 | — Heat Exchanger | 14 | — | Air Separator and Vent |
Fig. 11 — Typical Piping Diagram — 30RAP Units with Hydronic Package
13