N. FINAL ASSEMBLY OF GATE OPERATORFigure 13. Gate Operator Final AssemblyIMPORTANT SAFETY PROCEDURE

1.Turn off power to the gate operator at the circuit breaker and wait for one minute.

Refer to Figure 13, above, to perform the following instructions.

2.Disconnect Drag Link from Anchor. Then disengage quick disconnect by pulling the release lever on the Swing Arm Cap Assembly. Remove Swing Arm Cap Assembly and Drag Link Assembly from drive shaft. Set this assembly aside.

3.Install clear cover on gate operator control box.

4.Make sure that gate operator unit power switch is turned on.

5.Install gate operator cover and secure with four bolts.

6.Replace Swing Arm Cap Assembly and Drag Link Assembly on drive shaft, then reconnect Drag Link to gate Anchor.

7.Reinstall gate arm assembly onto output shaft/hub. Close red release lever until engagement pin fully seats into hub and ball plunger engages on handle. This may require slight side-to-side motion – HANDLE WILL CLOSE WHEN PIN IS PROPERLY ALIGNED – DO NOT FORCE SHUT.

8.Turn on power to the gate operator at the circuit breaker.

9.Cycle the gate to ensure it is operating properly.

22 of 42

Doc 01-20099

Rev F