installation into an approved masonry or zero clearance fireplaces, the use of single or double-wall flue pipe will not affect the clearance distance from the unit to any combustible materials.

 

 

 

 

 

 

 

 

 

DEFINED MINIMUM DISTANCESCLEARANCE

 

 

TO COMBUSTIBLES

 

 

 

 

 

 

 

 

 

 

 

A. UNIT TO SIDEWALL

7”

 

 

B. UNIT TO SIDE TRIM

7”

 

 

C. UNIT TOP TO TOP TRIM

9.25”

 

 

D. UNIT TOP TO MANTLE

9.25

 

 

E. HEARTH FLOOR TO MANTLE

32”

 

 

F. NONCOMBUSTIBLE FLOOR PROTECTION, front

6”

 

 

G. NONCOMBUSTIBLE FLOOR PROTECTION, sides

6”

 

 

 

 

 

 

 

 

 

TABLE 3: REQUIRED MINIMUM CLEARANCESSHROUD SYSTEM

FIGURE 11 shows the Country Flame shroud system. Black trim is standard and gold trim is OPTIONAL and must be ordered separately. New home construction normally will not require a shroud kit for the Crossfire because the fireplace opening can be finished out to exact Crossfire dimensions. For pre-existing installation, a Crossfire shroud kit is available and recommended. Country Flame offers three variations of shroud kit a) standard, b) oversize, and c) custom shroud. Standard and oversize shrouds are available through a Country Flame Dealer and customer shrouds can be ordered from Country Flame. Custom shrouds take 4 to 6 weeks to manufacture and require prepayment. Each Crossfire shroud comes with installation instructions and all required hardware. Contact a Country Flame Dealer for further details.

CF04-9200 (standard, 41.5” by 29.5” max opening) Shroud Kit Includes:

3SHROUD PANELS, (Top, Left Side, Right Side, each painted black)

3BLACK TRIM PIECES, (Top, Left Side, Right Side, pre-cut)

2TRIM CORNER BRACKETS with Screws

1ROLL OF FIBERGLASS INSULATION

CF04-9210 (oversized, fits 47.5” by 32.0” max opening) Shroud Kit Includes:

3SHROUD PANELS, (Top, Left Side, Right Side, each painted black)

3BLACK TRIM PIECES, (Top, Left Side, Right Side, pre-cut)

2TRIM CORNER BRACKETS with Screws

2ROLLS OF FIBERGLASS INSULATION

SHROUD INSTALLATION INSTRUCTIONS

1.Complete the Crossfire chimney and combustion air (if required) installation before installing the Crossfire shroud. The Crossfire insert should be sitting in the hearth ready for positioning in its final location but pulled forward as far as the chimney connection will allow. Open both the left and right access doors on the Crossfire. The installer can now begin installation of the shroud.

2.Remove the two ¼-20nuts and washers from the top of the Crossfire insert shroud mounting studs located on the top of the Crossfire hopper. Install the top shroud panel (as shown in FIGURE 11a) making sure the slots in the top shroud mounting flange are positioned over the mounting studs located on top of the Crossfire hopper. Now install the two washers and then the ¼-20nuts onto the studs. Do NOT tighten yet. Once installed, the nuts will hold the top shroud in place on the Crossfire until the top shroud is adjusted in it final position. The top