INSTALLING

3.

Pressurize supply piping system by either using compressed air or opening

 

Continued

 

main gas valve located on or near gas meter.

4.

Check all joints of gas supply piping system. Apply mixture of liquid soap and

 

 

water to gas joints. Bubbles forming show a leak.

5.Correct all leaks at once.

6.Re-connect heater and manual shutoff valve to gas supply. Check re-connected fittings for leaks.

Test Pressures Equal To or Less Than 1/2 PSIG

1.Close manual shutoff valve (see Figure 13).

2.Pressurize supply piping system by either using compressed air or opening main gas valve located on or near gas meter.

3.Check all joints from gas meter to manual shutoff valve (see Figure 14). Apply mixture of liquid soap and water to gas joints. Bubbles forming show a leak.

4.Correct all leaks at once.

Pressure Testing Heater Gas Connections

1.Open manual shutoff valve (see Figure 13).

2.Open main gas valve located on or near gas meter.

3.Make sure control knob of heater is in the OFF position.

4.Check all joints from manual shutoff valve to control valve (see Figure 14). Apply mixture of liquid soap and water to gas joints. Bubbles forming show a leak.

5.Correct all leaks at once.

6.Light heater (see Operating Heater, pages 19 through 22). Check all other internal joints for leaks.

7.Turn off heater (see To Turn Off Gas to Appliance, page 21).

Open

Manual

Shutoff

Valve

Closed

Figure 13 - Manual Shutoff Valve

Manual

Thermostat Gas Valve or

Shutoff

Control Valve Location

Valve

 

Gas Meter

 

Figure 14 - Checking Gas Joints

17

103343

Page 17
Image 17
Desa CGD3924NR installation manual Installing, Test Pressures Equal To or Less Than 1/2 Psig