2. Pull cables

2. Pull cables

The following cables need to be installed:

CAT 5 cables for signal transmission from the A/V Wall plates to the PVS 204SA.

NFor PVT RGB D Wall plates, two CAT 5 signal cables for each input are needed.

Maximum distance from the PVS 204SA to the Wall plates is 100 feet. The optimum distance is between 50 and 75 feet.

The CAT 5 cables supplied are terminated to the TIA 568A standard. Other CAT 5 cables can be used if they are TIA 568A or 568B standards and terminated to the same standard at both ends.

CAT 5 cables for MLC network connection

PoleVault switcher communication cable from the

MediaLink controller

Projector communication cables from the

MediaLink controller.

a.Drill cable pathways through any obstructions (e.g., wall caps, fire-breaks, or horizontal studs).

b.Label the CAT 5 signal cables at both ends with the supplied labels. Refer to the PVS 204SA User’s Manual for labeling details.

c.Pull the cabling through the wall from the ceiling space down to the location of the transmitters and other wall devices, and out through the openings.

TSecure cables with cable clamps to provide strain relief.

Trim back the outer foil shield to the point where the cable exits the cable clamp, and insulate exposed cable shields with heat shrink to reduce the chance of short circuits.

Both braided and foil shields should be connected to an equipment ground at the other end of the cable.

NOTE Fasten the colored section to the cable first, then wrap the clear section around it.

RGB #1A

2b Use the supplied labels for clear cable identification during installation.

Signal Cable

Label color

 

 

RGB 1A (Input 1 RGB)

Orange

 

 

RGB 1 B (Input 1 RGB)

Orange w/black stripe

 

 

RGB 2A (Input 2 RGB)

Yellow

 

 

RGB 2B (Input 2 RGB)

Yellow w/black stripe

 

 

Video 3 (Input 3 Composite Vid)

Green

 

 

Video 4 (Input 1 Composite Vid)

Red

 

 

2c Pull the cables at each location.

PoleVault Systems Installation • Installation — Stage 2

2-11