3 Commissioning the switchgear
Installing and starting up the switchgear is an important event for the System Administrator. The
following steps must be followed when commissioning the switchgear.
Step 1: Reset Passwords.
See Passwords on page 13.
Step 2: Set User Settings.
See DEH-231 Entellisys Low Voltage Switch gear System User Manual.
Step 3: Set Local HMI flags.
See Local HMI onpage 17.
Step 4: Set System Time Sy nchronization.
See Time synchronization onpage 19.
Step 5: Configure System for Rem ote Communications.
See Configuring the swi tchgear for remote communication s on page21.