Installation Overview

Filler Panels

1.Unpack the hood and lay it on the lifting skid.

2.Bolt the filler panels together with 5/16 in. bolts provided in the hardware package.

3.Position the filler panels to the hood back, and tack-weld them into place.

4.To allow for ease of cleaning, caulk the external seams with NSF Approved silicone caulk

(GE SCS1000, or its equivalent). The caulk is not provided.

Hood

Hood

Hood

 

Right Filler Panel

Tack-welded to

 

hood back

Bottom Filler Panel

 

5/16 inch x 3/4 inch bolts with washers and nuts

NOTE

If you have a Back Supply Plenum (BSP), this must be installed before the hood. Refer to page 11 for instructions on installing the BSP.

NOTE

All hanger brackets must be used and the hood must be properly supported while lifting to prevent damage or distortion to the hood. The hood must be hung level to operate properly.

After the hood is secured, make the exhaust duct connections. The fire system distributor must be contacted at this time. After the fire system has been installed, mount the enclosures, then the supply plenums. If an Horizontal Supply Plenum is provided, it should be installed before the enclosures. The hood and accessories are now installed.

Finally, make the electrical connections from the controls to the fans and complete the fire system circuits as required by the job specification (job specific wiring diagram located inside the cabinet cover).

®