Installation procedure
Install indoor unit
Insert into the water supplying pipe 20mm~30mm (insert the drain hose toward bottom)
|
|
| Pour water into the |
|
| Install the drain hose clamp | protruding connector |
| Main unit | Drain hose |
|
Remove the rubber |
|
|
|
stopper, after |
|
|
|
finishing installation, | Check the condition of drainage |
| |
it must be reinstalled | through the transparent hose base |
|
Before finishing the wiring work, install a protruding connector on the drain hose to provide a water in hole. Then, if there is water leaks from the pipe system, perform check. Finally, the water flow through the drain hose should normally pass.
6. Installation of air suction and discharging duct
Please consult the
of suction inlet, suction duct, di- scharging outlet and discharging duct. Calculating the design dra- wing and outer static pressure, and choose the discharging duct with proper length and shape.
Main unit of air conditioner
The surface | Insulator |
|
|
| |
of ceiling |
| Special air in nozzle |
| Checking hole | (locally bought) |
|
| attached with air filter |
| Air discharging | Air in pipe |
| pipe (locally bought) | (locally bought) |
The length difference among | Incorrect | Incorrect | Correct | |
every duct is limited below 2:1. | ||||
|
|
| ||
Reduce the length of duct as possible as can. |
|
|
| |
Reduce the amount of bend as possible as can. |
|
|
|
Use heat insulation material to bind and seal the part connecting main unit and the flare part of air discharging duct. Perform duct installation work, before the fitment of ceiling.
7. Connection of air suction and discharging duct
(a)Absorb of fresh air (single air supplying) (b)Air discharging
Use side air absorbing nozzle or absorb from the air in pipe
Use side air discharging nozzle (do use together with air absorbing)
Connection pipe side
Side air absorbing | side |
| Connection pipe |
Absorb from the air in pipe
Air discharging nozzle
Do not use this nozzle for air in
Absorb from the air in pipe
(c) Perform thermal insulation to the duct to prevent from frosting