Heat Controller DMH12SB-0, DMC18SB-1, DMC12SB-0 Evacuation, Finishing the job, Installation

Models: DMH12SB-0 DMH18SB-1 DMC24SB-1 DMH24SB-1 DMH09SB-0 DMC09SB-0 DMC12SB-0 DMC18SB-1

1 73
Download 73 pages 60.73 Kb
Page 31
Image 31
Evacuation

Installation

 

Soap water method

 

 

 

 

the gas side and liquid side

 

Suction Line

(1) Remove the caps from

 

 

valves.

 

 

(2)Remove the service-port cap from the gas side valve.

(3)

To open the gas side valve turn the valve stem

 

 

counterclockwise approximately 90°, wait for about

Evaporator Line

 

2~3 seconds, and close it.

3-way valve

(4)

Apply a soap water or a liquid neutral detergent on

(Close)

 

the indoor unit connection or outdoor unit connec-

 

 

tions by a soft brush to check for leakage of the con-

3-way valve

 

necting points of the piping.

(Open)

(5) If bubbles come out, the pipes have leakage.

Evacuation

Cap

 

• Connect the charge hose end described in the

 

Hexagonal wrench

 

 

 

 

 

preceding steps to the vacuum pump to evacuate

 

 

 

 

the tubing and indoor unit.

 

 

 

 

Confirm the "Lo" knob of the manifold valve is

 

 

 

 

open. Then, run the vacuum pump.

 

 

Indoor unit

 

The operation time for evacuation varies with tub-

 

 

 

 

ing length and capacity of the pump. The follow-

 

 

 

 

ing table shows the time required for evacuation.

 

 

 

 

Required time for evacuation when 4 CMF vacu-

 

 

 

 

um pump is used

 

 

 

 

If tubing length is less

if tubing length is longer

 

 

 

 

than 10m (33 ft)

than 10m (33 ft)

 

 

 

 

10 min. or more

15 min. or more

 

 

Outdoor unit

 

• When the desired vacuum is reached, close the

 

 

 

 

"Lo" knob of the manifold valve and stop the vac-

 

 

 

 

uum pump.

 

 

 

 

 

Finishing the job

 

 

 

 

• With a service valve wrench, turn the valve stem

 

 

 

 

of liquid side valve counter-clockwise to fully

Manifold valve

 

open the valve.

 

 

 

 

 

• Turn the valve stem of gas side valve counter-

Pressure

Lo

Hi

 

clockwise to fully open the valve.

gauge

 

 

 

 

 

 

 

• Loosen the charge hose connected to the gas

 

 

 

 

side service port slightly to release the pressure,

Open

 

Close

 

then remove the hose.

 

 

 

 

• Replace the flare nut and its bonnet on the gas

 

 

 

 

side service port and fasten the flare nut securely

 

 

 

 

with an adjustable wrench. This process is very

 

 

 

 

important to prevent leakage from the system.

 

 

 

 

• Replace the valve caps at both gas and liquid

Vacuum pump

 

side service valves and fasten them tight.

 

 

 

 

 

This completes air purging with a vacuum pump.

 

 

 

 

The air conditioner is now ready to test run.

 

 

 

 

 

 

 

 

Service Manual